Power utilities promised smoother land allocation

Two years after it signed memoranda with several independent power producers (IPPs) to generate 12,500 MW,. reports Dharmendra Jore.

Updated on: Apr 10, 2007 03:33 AM IST
None | By , Mumbai
Prefer HTon Google
Advertisement

Two years after it signed memoranda with several independent power producers (IPPs) to generate 12,500 MW, the state government has stepped in to resolve the issue of land allocation to them.

HT Image
HT Image

On Monday, Revenue Minister Narayan Rane and Energy Minister Dilip Walse-Patil assured a smoother land acquisition process after Chief Minister Vilasrao Deshmukh passed directives last month.

In March 2005, the state signed a deal with Reliance Energy Limited (REL) for a 4,000 MW plant. The Tata Power Company (TPC) and Essar too signed MoUs for two 1,500 MW power plants. GMR, Ispat and Jindal each signed deals to put up three 1,000 MW power plants while Spectrum agreed to build a 500 MW capacity plant in the state.

REL and TPC completed all formalities last year and identified land in Shahpur near Alibaug in Raigad district. However, lack of coordination between the revenue and industry departments led to an overlap of 1,000 acres of land that was to be allocated to both the companies.

Private participation in power generation is a necessity for the state, which faces a deficit of a staggering 5,500 MW. With each passing year, the deficit is expected to rise by 1,000 MW. Even if half of the IPPs (that have signed memoranda with the state) start generating power in the next four years, the state will benefit from the additional power.

 
Check India news real-time updates, latest news on Hindustan Times and more across India.
Check India news real-time updates, latest news on Hindustan Times and more across India.
SHARE THIS ARTICLE ON
Hindustantimes wants to start sending you push notifications. Click allow to subscribe