No lessons learnt from 2005 flood

After the July 2005 floods, several projects were announced, including the revival of the ambitious Brimstowad project. Seven years later, only two pumping stations are ready, and only 15 of 58 Brimstowad projects are complete reports Poorvi Kulkarni.

Updated on: Jun 08, 2013 01:10 AM IST
Hindustan Times | By , Mumbai
Prefer HTon Google
Advertisement

After the July 2005 floods, the Brihanmumbai Municipal Corporation (BMC) publicly declared its intent to rid the city of flooding, one step at a time. Several projects were announced, including the revival of the ambitious Brimstowad project for a complete overhaul of the city’s drain network and proposal for eight pumping stations to pump out flood water.

HT Image
HT Image

Seven years later, only two pumping stations are ready, and only 15 of 58 Brimstowad projects are complete.

These, among other long-term measures for a permanent solution to flooding, have been brazenly ignored, but the civic body continues to spend crores every year for desilting nullahs.

The civic body’s approach to flood relief has been myopic – while it stepped up several short-term measures, such as upgrading its disaster management cell, installing dewatering pumps at flood-prone spots and setting up a monsoon website to guide citizens about traffic and water logging situation during rains, among others, the same urgency was not shown for the bigger picture.

Experts insist the BMC should have focused on a permanent solution. "The approach was to boost the disaster-control mechanisms and flood-control measures instead of flood prevention. There needs to be a sustained effort to speed up long-term projects," said SN Patankar, former chief engineer (storm water drains and roads). "A disaster similar to July 26 can still not be averted."

Civic officials, however, claimed that all possible efforts were being taken.

"We have imposed fines and sent notices but if we decide to terminate the contracts, we would have to begin the tendering process all over again. No decision has been taken towards that yet," said Laxman Vhatkar, chief engineer (storm water drains).

 
Catch every big hit, every wicket with Crickit, a one stop destination for Live Scores, Match Stats, Infographics & much more. Explore now!

Stay updated with all the Breaking News and Latest News from Mumbai. Click here for comprehensive coverage of top Cities including Bengaluru, Delhi, Hyderabad, and more across India along with Stay informed on the latest happenings in World News.
Catch every big hit, every wicket with Crickit, a one stop destination for Live Scores, Match Stats, Infographics & much more. Explore now!

Stay updated with all the Breaking News and Latest News from Mumbai. Click here for comprehensive coverage of top Cities including Bengaluru, Delhi, Hyderabad, and more across India along with Stay informed on the latest happenings in World News.
SHARE THIS ARTICLE ON
Hindustantimes wants to start sending you push notifications. Click allow to subscribe