Poor cost calculation, planning led to 58% rise in cost of dam

Irregularities in preparation of cost estimates and poor planning is what could have caused a major drain of civic treasury funds being spent on the Middle Vaitarna dam project which promises an additional of 455 million litres of water to the city every day.

Updated on: Mar 16, 2013, 01:50:09 IST
Hindustan Times | By , Mumbai
Prefer HTon Google
Advertisement

Irregularities in preparation of cost estimates and poor planning is what could have caused a major drain of civic treasury funds being spent on the Middle Vaitarna dam project which promises an additional of 455 million litres of water to the city every day.

HT Image
HT Image

A 58% escalation in cost amounting to Rs. 900 crore has been incurred by the Brihanmumbai Municipal Corporation (BMC) in a span of five years since tenders were invited for the project in 2007.

When it is ready in May, the dam will help the city make up for a shortfall of 700 million litres per day that it currently faces.

Justifying the variation in costs, Ramesh Bhambale, deputy municipal commissioner (special engineering), said: “The rise in cost was not foreseen when the initial estimates were prepared and the project was mooted. But we had to keep pace with the changes in the nature of work that we came across from time to time as work progressed.”

Opposition parties have slammed the civic administration for approving such enormous cost escalation without contemplating any action against the contractors or officials responsible for this unchecked spending of taxpayers’ money.

He also alleged covert links between powerful politicians and influential bureaucrats for the execution of the mega project that has drained taxpayers’ money.

HT had reported in January how recurrent delays in the completion of a bridge near the dam undertaken by the state public works department had also cost the BMC 40% more than estimated. “Funds of crores of rupees have been sapped for the project. There is a need for the administration to issue a detailed clarification on the delays and cost variations in the project,” said Manoj Kotak, BJP corporator and standing committee member.

 
Catch every big hit, every wicket with Crickit, a one stop destination for Live Scores, Match Stats, Infographics & much more. Explore now!

Stay updated with all the Breaking News and Latest News from Mumbai. Click here for comprehensive coverage of top Cities including Bengaluru, Delhi, Hyderabad, and more across India along with Stay informed on the latest happenings in World News.
Catch every big hit, every wicket with Crickit, a one stop destination for Live Scores, Match Stats, Infographics & much more. Explore now!

Stay updated with all the Breaking News and Latest News from Mumbai. Click here for comprehensive coverage of top Cities including Bengaluru, Delhi, Hyderabad, and more across India along with Stay informed on the latest happenings in World News.
SHARE THIS ARTICLE ON
Hindustantimes wants to start sending you push notifications. Click allow to subscribe