Chennai, Bengaluru, Pune have delayed flats worth 11,000 crore

According to JLL data, the real estate firms of Delhi-NCR are biggest defaulters as their contribution in delayed housing units accounts for 71% in volume and 56% in value terms. Kolkata has the least number of delayed units at 384 worth ₹288 crore.

Updated on: Aug 27, 2019 02:34 PM IST
Mumbai | By
Prefer HTon Google
Advertisement

New Delhi: Nearly 2.2 lakh housing units, worth 1.56 trillion, launched in 2011 and before across seven major cities are yet to be completed by real estate developers, according to property consultant JLL India.

NCR and Mumbai together contributed to 91% of the troubled units, JLL said in the report. (Mint photo)
NCR and Mumbai together contributed to 91% of the troubled units, JLL said in the report. (Mint photo)

According to JLL data, the real estate companies of Delhi-NCR are biggest defaulters as their contribution in delayed housing units accounts for 71% in volume and 56% in value terms. As many as 2,18,367 housing units valuing 1,55,804 crore are delayed and at various stages of construction in seven cities — Delhi-NCR, Mumbai, Chennai, Kolkata, Benagluru, Hyderabad and Pune.

Out of the nearly 2.2 lakh units, JLL said in a report that “about 30,000 units are confirmed to be scrapped”.

The consultant pointed out that the national capital region (Delhi-NCR) is facing delays in 1,54,075 units valuing 86,824 crore. As many as 43,449 units worth 56,435 crore are still incomplete in Mumbai.

“NCR and Mumbai together contributed to 91% of the troubled units,” JLL said in the report.

Total delayed units in Hyderabad stood at 2,095 worth 1,297 crore.

Kolkata has the least number of delayed units at 384 worth 288 crore.

In April this year, property consultant Anarock came out with a report that suggested that around 5.6 lakh housing units (worth 4.5 lakh crore) that were launched in 2013 and before in these seven cities were running behind the delivery timelines.

A significant delay in giving possession of apartments to homebuyers is one of the major reasons for demand slowdown in the housing segment. Lakhs of homebuyers are stuck in residential projects launched by developers such as Jaypee group, Amrapali and Unitech.

Homebuyers body Forum for Peoples’ Collective Efforts (FPCE) president Abhay Upadhyay said 5 lakh customers are stuck across the country due to delayed projects.

In a recent meeting called by the finance minister, he demanded creation of a 10,000 crore stress fund to complete such projects and provide relief to homebuyers.

 
Stay updated with latest Real Estate news and updates from India and around the World, explore the latest market moves and premium property listings updates now on Hindustan Times
Stay updated with latest Real Estate news and updates from India and around the World, explore the latest market moves and premium property listings updates now on Hindustan Times
SHARE THIS ARTICLE ON
Hindustantimes wants to start sending you push notifications. Click allow to subscribe