Haryana RERA denies Godrej Developers & Properties' application for Gurugram project's extension; freezes account

Godrej Promoters & Developers LLP said it is in the process of making a representation to the authority requesting it to set aside the interim directions

Published on: Apr 09, 2024 10:14 PM IST
Advertisement

Haryana’s real estate regulatory authority, Gurugram, has denied Godrej Developers & Properties application for extension of registration citing non-compliance of RERA norms.

Haryana’s real estate regulatory authority, Gurugram, has denied Godrej Developers & Properties application for extension of registration citing non-compliance of RERA norms. (Hindustan Times)
Haryana’s real estate regulatory authority, Gurugram, has denied Godrej Developers & Properties application for extension of registration citing non-compliance of RERA norms. (Hindustan Times)

The Authority said that despite several reminders, the promoter of the project, which is Godrej Developers & Properties LLP, failed to rectify the deficiencies in the application, which showed a mismatch of several details provided in the project's quarterly progress report (QPR) from those mentioned in the CA certificate. There were also deficiencies relating to license renewal and bank balance, Haryana RERA's order said.

The promoter is developing a group housing project Godrej Air Phase 4 in Sector 85, Gurugram.

The promoter had obtained the RERA registration in December 2018 and it was valid up to June 2023, by which the promoter had to complete the housing project.

Also Read: Haryana RERA revokes registrations of five real estate projects in Gurugram

The firm had applied with RERA Gurugram seeking further extension of the registration to complete the project, moving an application under Section 6 of the RERA Act.

During the scrutiny of the application, the Authority observed many deficiencies in the application and asked the promoter to rectify the same, Haryana RERA order said.

Also Read: Outline plan to complete 3 pending projects: HRERA to OSB developers

“Keeping in view the above facts, the Authority rejects the application for extension of registration of the project. Further, the bank account of the project be frozen and a compliance letter to this effect be sent to the Bank,” the Authority’s order said.

The Authority has also warned the promoter against creating any third-party rights and has cautioned the general public to refrain from booking any property in the project, the order said.

Also Read: Banks to ensure builders comply with RERA norms when handling public money

Godrej's response

Godrej Promoters & Developers LLP had filed an application for grant of extension of RERA Registration Certificate for its project Godrej Air Phase 4 (Retail), wherein requirement of certain compliances were raised by the Hon’ble Authority, a spokesperson of the company said.

"We have continuously been responding to the queries raised by the Authority and we have been submitting the relevant documents with the Authority. We are in the process of making a representation in front of the authority requesting them to set aside the interim directions passed in this order,” said the company spokesperson.

 
ABOUT THE AUTHOR
HT News Desk

Follow the latest breaking news, major developments and agenda-setting stories from India and around the world with the newsdesk at Hindustan Times. Operating round the clock, the desk brings together experienced editors, reporters and correspondents to deliver fast, accurate and contextual reporting across subjects that influence public policy, governance, business, society and international affairs. The HT News Desk covers politics, elections, government policies, the economy, business and markets, science and technology, the environment, law and order, infrastructure, education, climate issues and geopolitics, while closely tracking developments across states, institutions and global capitals. The team also leads coverage of major breaking news events, policy announcements, court proceedings, natural disasters, public emergencies and significant international developments. Reports published by the newsdesk are based on information gathered from reporters on the ground, official statements, government agencies, court records, regulatory filings, recognised institutions and other authoritative sources. Stories undergo editorial scrutiny and verification processes to ensure accuracy, fairness and relevance, and are updated as events evolve and additional information becomes available. Whether covering a key political decision in New Delhi, an economic policy shift affecting millions, a landmark court ruling or a major global event, the HT News Desk aims to provide readers with reliable, fact-based journalism that delivers not only the latest developments but also the context and analysis needed to understand their wider implications.

Stay updated with latest Real Estate news and updates from India and around the World, explore the latest market moves and premium property listings updates now on Hindustan Times
Stay updated with latest Real Estate news and updates from India and around the World, explore the latest market moves and premium property listings updates now on Hindustan Times
SHARE THIS ARTICLE ON
Hindustantimes wants to start sending you push notifications. Click allow to subscribe