The land acquisition process for the Arcellor Mittal’s proposed Rs 42,000 crore green field integrated steel plant in Jharkhand has already begun, a senior state government official said in Adityapur on Tuesday.

Updated on: Mar 29, 2011 03:39 PM IST
Advertisement

The land acquisition process for the Arcellor Mittal’s proposed Rs 42,000 crore green field integrated steel plant in Jharkhand has already begun, a senior state government official said in Adityapur on Tuesday.

HT Image
HT Image

The land registration for the proposed steel plant of Arcellor Mittal has begun in Kasmar Petrawar in Bokaro district since December last, said Jharkhand Industry Secretary, A P Singh, who was here to take part in the inauguration of Hi-Tech Design Lab and foundation stone laying ceremony of Hi-Tech Testing Lab building on Tuesday, said.

The land acquisition process had been tardy due to Panchayat election and the National Games that concluded last month but the process has now got momentum, Singh said on the sidelines of the foundation stone laying ceremony.

Asked how many of acres of land has been registered so far, the Industry secretary said it was below 50 acres and attributed the slow pace of land registration process due to panchayat election and National Games.

Arcellor Mittal requires 2200 acres land to start work for the first phase, he said.

Arcellor Mittal had signed a memorandum of understanding with the Jharkhand government for the proposed steel plant in October 2005.

 