CAG points out poor resurfacing work at Leh air force station

The Comptroller and Auditor General (CAG) has indicted the air force for poor quality of runway re-surfacing work at the Leh air force station, which is the highest airfield in the world, in its latest report. The report was tabled in the Parliament on July 18.

Updated on: Jul 25, 2014 04:08 PM IST
Hindustan Times | By , Chandigarh
Prefer HTon Google
Advertisement

The Comptroller and Auditor General (CAG) has indicted the air force for poor quality of runway re-surfacing work at the Leh air force station, which is the highest airfield in the world, in its latest report. The report was tabled in the Parliament on July 18.

HT Image
HT Image

The work on runway resurfacing was sanctioned by the ministry of defence in March 2009 at an estimated cost of Rs 29.39 crore to be completed in three working seasons (in Leh, the working season is of just six months).

The subsequent change in design was sought and the contract was revised to Rs 33.59 crore and then to Rs 34.45 crore after getting approval. However, the work was completed in October 2011 at a cost of Rs 36.12 crore.

“After completion of work, it was noticed by the users (air force station of Leh) that the runway suffered continuous degradation due to surface wear and tear. Temporary repairs were carried out in March 2012 by the contractor at no extra cost,” reveals CAG.

“We observed in February 2013 that degradations were noticed again in December 2012. Joint inspection at station level carried out in January 2013 in association with General Reserve Engineer Force (GREF) revealed that to enhance the life of runway, additional cost of Rs 3.22 crore would be required for temporary restoration and 10.21 crore for permanent measures,” says CAG report.

When objection was raised, chief engineer, stated in March 2013 that the surface was damaged “due to unconventional method under which salt and other chemicals were used by the General Reserve Engineer Force (GREF) for removal of accumulated snow from the surface”.

The final decision on whether temporary restoration or permanent measure to repair the runway to be adopted was pending in March 2013 with air force station authorities, says CAG report.

It concluded, “The reply given by the chief engineer is not acceptable since the resurfaced runway at the station had shown degradation of surface immediately after completion of the resurfacing work. The subsequent change in the design involving an additional expenditure of Rs 5.06 crore also did not prove effective and the degraded runway was yet (March 2013) to be made good.”

 
ABOUT THE AUTHOR
Bhartesh Singh Thakur

Bhartesh Singh Thakur is a senior correspondent at Chandigarh. He covers Panjab University, local administration and defence.

SHARE THIS ARTICLE ON
Hindustantimes wants to start sending you push notifications. Click allow to subscribe