AAP MLA-elect Prashar inspects project to cover Shivaji Nagar nullah

The ₹17.85-crore project to cover 1.4 kilometres of the nullah (Transport Nagar to Shingar Cinema Road) was initiated in September 2020, and it was estimated that the work would be complete by March 2022

Published on: Mar 16, 2022 01:46 AM IST
Advertisement

A day after carrying out a surprise inspection at the civil hospital, AAP MLA-elect (Ludhiana Central) Ashok Prashar ‘Pappi’ inspected the ongoing work of covering the nullah (drain) passing through Shivaji Nagar on Tuesday.

Residents have been complaining about the slow pace of the project, and the unhygienic conditions they are being forced to live in as a result. Choked sewer lines due to the ongoing work and contaminated water supply have driven residents up the wall. (HT Photo)
Residents have been complaining about the slow pace of the project, and the unhygienic conditions they are being forced to live in as a result. Choked sewer lines due to the ongoing work and contaminated water supply have driven residents up the wall. (HT Photo)

Residents have been complaining about the slow pace of the project, and the unhygienic conditions they are being forced to live in as a result. Choked sewer lines due to the ongoing work and contaminated water supply have driven residents up the wall.

The 17.85-crore project to cover 1.4 kilometres of the nullah (Transport Nagar to Shingar Cinema Road) was initiated in September 2020, and it was estimated that the work would be complete by March 2022. However, residents say that the project will most certainly miss the deadline, and that action should be taken against the officials concerned, and the contractor.

MC Officials say the delay in shifting electricity poles and transformers was responsible for the delay. A meeting will also be held with officials of Punjab State Power Corporation Limited (PSPCL) to expedite the process to shift the poles.

Prashar said directions had been issued to MC officials and the contractor to expedite the project. “A meeting will be held with officials of MC and PSPCL in the coming days to ensure that the project is completed without hurdles. I will be monitoring the work.”

 