HP govt sets March 2021 as new deadline for Parwanoo-Shimla highway project

The NH expansion project has hit a series of roadblocks in the past few years, ranging from lack of coordination among the executing agencies, labour shortage during Covid-19 pandemic to delay in land acquisition and repeated landslides.

Updated on: Oct 29, 2020 10:12 PM IST
Hindustan Times, Shimla | By , SHIMLA
Prefer HTon Google
Advertisement

Already running two years behind schedule, the first phase of Parwnoo-Solan highway four-laning project has been granted six more months for completion.

Chief minister Jai Ram Thakur reviewing various projects during a meeting of the state public works department in Shimla on Thursday. (HT Photo)
Chief minister Jai Ram Thakur reviewing various projects during a meeting of the state public works department in Shimla on Thursday. (HT Photo)

The Himachal government on Thursday declared March 31, 2021, as the new deadline after the one in September this year was missed.

Meant to curtail travel time to Shimla, the four-laning work, as part of the Parwanoo-Shimla highway expansion project, has hit a series of roadblocks in the past few years, ranging from lack of coordination among the executing agencies, labour shortage during Covid-19 pandemic to delay in land acquisition and repeated landslides.

Chief minister Jai Ram Thakur, who also holds the public works department (PWD) portfolio, has directed the National Highways Authority of India (NHAI) to complete the first phase latest by March 31, 2021.

“I have given instructions for completion of the project within a time frame so that cost escalation is avoided,” said Thakur while reviewing the progress of different road projects here on Thursday.

The CM asked the officials to complete the Kiratpur-Nerchowk road widening project by March next year.

Work on the second phase from Solan to Kaithlighat is scheduled to be completed by May next year. The estimated project cost is Rs 598 crore. So far, only 28% of the work has been done.

‘Finish patchwork before winter’

While reviewing other works, Thakur directed the officials to take up patchwork on the stretch between Nerchowk and Kullu at the earliest keeping in view the winter season. He said that upgradation work on Jogindernagar-Pathankot road, Baddi-Nalagarh and Pinjore-Nalagarh should be expedited and completed within the stipulated period. He also stressed the need for plantation of saplings alongside roads to turn them into green highways.

He also expressed his concern over the delay in construction of bridge over Beas river in Manali which was causing inconvenience to both tourists and locals. He directed the authorities concerned to speed up the work.

 
ABOUT THE AUTHOR
Gaurav Bisht

Gaurav Bisht heads Hindustan Times’ Himachal bureau. He covers politics in the hill state and other issues concerning the masses.

Stay updated with all the breaking news and latest News from Mumbai. Track comprehensive coverage of top cities across India including Bengaluru, Delhi (including Sonam Wangchuk Hunger Strike LIVE),and more, along with staying informed on the latest happenings.
Stay updated with all the breaking news and latest News from Mumbai. Track comprehensive coverage of top cities across India including Bengaluru, Delhi (including Sonam Wangchuk Hunger Strike LIVE),and more, along with staying informed on the latest happenings.
SHARE THIS ARTICLE ON
Hindustantimes wants to start sending you push notifications. Click allow to subscribe