...
...
Next Story

Kharar flyover’s completion pushed to November as labour shortage hits work

Since construction began in December 2015, the project has missed six deadlines due to various roadblocks

Updated on: May 30, 2020 02:51 AM IST
Hindustan Times, Mohali | By , Mohali
Prefer HTon Google
Advertisement

Expected to be completed by September after missing multiple deadlines, the Kharar flyover has been delayed again — this time by two more months, now getting the seventh deadline as November 2020.

In the past over four years, only 70% work has been completed on the flyover in Mohali. (Gurminder Singh/HT)
In the past over four years, only 70% work has been completed on the flyover in Mohali. (Gurminder Singh/HT)

The National Highway Authority of India (NHAI) had handed over the Rs 368-crore project to Larsen & Toubro, that began construction in November 2015. It was to be completed in three years by December 2018.

But over four years later, only 70% work has been completed, with the project being pushed six times to January 2020, March, June, July, September and now to November.

After multiple roadblocks impeding the project’s progress, authorities have now cited labour shortage and shifting of the overhead high-tension power cables as reasons for further delay.

Work on the flyover was suspended on March 22 after the nationwide lockdown to prevent the spread of Covid-19, but was resumed from April 20, with authorities hoping it will finish by September amid restrictions on movement of traffic.

NHAI project director Krishnan Sachdeva said they were doing their best to complete the project by November end. “Due to Covid-19 lockdown, we are working with only 50% manpower, as the remaining workers have returned to their native states,” he said.

The national highway where the flyover is coming up connects Chandigarh to parts of Punjab, besides Jammu and Kashmir and Himachal Pradesh.

This leaves Kharar as a major bottleneck, with around 50,000 vehicles crossing the stretch daily.

“The authorities concerned are not bothered about the inconvenience to commuters and keep indulging in blame game. It is a challenge to cross the stretch, which often even delays ambulances,” said Kamaldeep Singh Tiwana, a resident of Kharar.

Project file

It entails widening of the road between Balongi and Kharar T-point, including two flyovers and three minor bridges.

Length: 10.2km

Cost: Rs 368 crore

Construction began: November 2015

First deadline December 2018

Second deadline January 2020

Third deadline March 2020

Fourth deadline June 2020

Fifth deadline July 31

Sixth deadline September 30

Fresh deadline November

Work Completed 70%

 
ABOUT THE AUTHOR
Hillary Victor

Hillary Victor is a Special Correspondent at Chandigarh. He covers Chandigarh administration, municipal corporation and all political parties.

Stay updated with all top Cities including, Bengaluru, Mumbai, on Hindustan Times and more across India.
Stay updated with all top Cities including, Bengaluru, Mumbai, on Hindustan Times and more across India.
SHARE THIS ARTICLE ON
Hindustantimes wants to start sending you push notifications. Click allow to subscribe