Mulund Slab Collapse: ‘Result of hiring the lowest bidder’

While citizens have underscored the laxity of contractors and general consultants “who are paid crores of public money to monitor the works”, urban planners, infrastructure and transport experts have questioned the protocols being followed by them.

Published on: Feb 15, 2026, 06:00:05 IST
Advertisement

MUMBAI: Saturday afternoon’s incident of a concrete slab collapsing from the elevated Metro -4 site in Mulund has angered Mumbaikars, with most of them raising questions over safety protocols followed by Mumbai Metropolitan region Development Authority (MMRDA) and its contractors who deploy workers at various metro sites in the Mumbai Metropolitan Region (MMR).

iMumbai, India - February 14, 2026: A portion of a Metro rail track pillar in north-east Mumbai’s Mulund West collapsed on Wednesday. At least 3 persons could be injured in the incident. The track, from which a slab fell, was under construction. The incident reportedly occurred along LBS Marg in Mumbai, India, on Saturday, February 14, 2025. (Photo by Satish Bate/ Hindustan Times) (Hindustan Times)
iMumbai, India - February 14, 2026: A portion of a Metro rail track pillar in north-east Mumbai’s Mulund West collapsed on Wednesday. At least 3 persons could be injured in the incident. The track, from which a slab fell, was under construction. The incident reportedly occurred along LBS Marg in Mumbai, India, on Saturday, February 14, 2025. (Photo by Satish Bate/ Hindustan Times) (Hindustan Times)

While citizens have underscored the laxity of contractors and general consultants “who are paid crores of public money to monitor the works”, urban planners, infrastructure and transport experts have questioned the protocols being followed by them.

MMRDA is currently carrying out works on eight different metro corridors that are part of its overall 337-kilometer network. An activist and an eyewitness of the incident alleged that “labourers working on the Metro-4 site here cut the concrete slab wall instead of welding it”.

AV Shenoy, member, Mumbai Mobility Forum said: “Going for lowest of all quotations – the L1 system (or the lowest bidder) -- makes contractors use substandard material to cut costs. It seems there is no active supervision by MMRDA engineers to ensure quality, and the total dependence is on contractors and external consultants to maintain quality.”

Referring to the present incident in Mulund, Desai said, “An independent structural audit should be done of all the structural elements at metro sites, considering that most incomplete columns, viaduct, station slabs, etc are at least five or more years old.”

An MMRDA official, who did not wish to be named, said that it is the responsibility of the “general consultant is to ensure that the ongoing works are undertaken with adequate safety measures and protocols, and to keep a check on the day-to-day activities of the consultant carrying out the work, which is why they are paid crores of public money”.

 
Catch every big hit, every wicket with Crickit, a one stop destination for Live Scores, Match Stats, Infographics & much more. Explore now!

Stay updated with all the Breaking News and Latest News from Mumbai. Click here for comprehensive coverage of top Cities including Bengaluru, Delhi, Hyderabad, and more across India along with Stay informed on the latest happenings in World News.
Catch every big hit, every wicket with Crickit, a one stop destination for Live Scores, Match Stats, Infographics & much more. Explore now!

Stay updated with all the Breaking News and Latest News from Mumbai. Click here for comprehensive coverage of top Cities including Bengaluru, Delhi, Hyderabad, and more across India along with Stay informed on the latest happenings in World News.
SHARE THIS ARTICLE ON
Hindustantimes wants to start sending you push notifications. Click allow to subscribe