Opening of Bajghera flyover not possible before September 30, railway work still incomplete

The PWD is also the custodian authority of the road leading from Krishna Chowk (near Palam Vihar C 1 Block) to Delhi via Bajghera railway crossing, New Palam Vihar and Bijwasan, on which the flyover is being built. A team of PWD officials inspected progress of the work on Friday.

Updated on: Aug 09, 2019 11:48 PM IST
Advertisement

The flyover and underpass being constructed at the Bajghera railway crossing may not be opened before September 30, a senior official of the Indian Railways said. However, the public works department (PWD), which is the custodian authority of the project, wants the flyover opened by August 31.

The flyover and underpass being constructed at the Bajghera railway crossing may not be opened before September 30, a senior official of the Indian Railways said.  (Photo by Parveen Kumar/Hindustan Times)
The flyover and underpass being constructed at the Bajghera railway crossing may not be opened before September 30, a senior official of the Indian Railways said. (Photo by Parveen Kumar/Hindustan Times)

The PWD is also the custodian authority of the road leading from Krishna Chowk (near Palam Vihar C 1 Block) to Delhi via Bajghera railway crossing, New Palam Vihar and Bijwasan, on which the flyover is being built. A team of PWD officials inspected progress of the work on Friday.

The PWD is constructing approach roads on both sides of the railway line, while the central portion of the flyover and underpass being constructed by the Indian Railways itself.

The central portion of the flyover is incomplete — girders are yet to be placed over the railway tracks to join the approach roads.

There are six steel-frame girders — each roughly 50-metres long — which will be placed over the railway tracks. The railways’ three girders are ready, and the rest are yet to be assembled.

In December 2016, the PWD had begun construction of the flyover and underpass with a December 2018-deadline. Traffic between Delhi and Gurugram via the Bajghera railway crossing has been blocked since then.

“Our deadline is August 31, as we discussed with the Railways and I have asked the railways to adhere to the timeline,” said Chandra Mohan, superintending engineer PWD.

Residents said they are hopeful the projects wrap up soon, and traffic on the crossing reopened.

Yasheesh Yadav, resident Mahindra Aura Sector 110-A, said, “After this crossing was blocked, we use Chauma and Daulatabad crossings which are choked most of the time and far away from our society. We wish PWD open flyover at earliest.”

 
ABOUT THE AUTHOR
Dhananjay Jha

Dhananjay Jha writes on development authorities, transport, industries, power and other developmental issues in Gurgaon. A journalist for over a decade, he has worked in Delhi and in HT’s Noida bureau.

Catch every big hit, every wicket with Crickit, a one stop destination for Live Scores, Match Stats, Infographics & much more. Explore now!.

Stay updated with all the Breaking News and Latest News from Mumbai. Click here for comprehensive coverage of top Cities including Bengaluru, Delhi, Hyderabad, and more across India along with Stay informed on the latest happenings in World News.
Catch every big hit, every wicket with Crickit, a one stop destination for Live Scores, Match Stats, Infographics & much more. Explore now!.

Stay updated with all the Breaking News and Latest News from Mumbai. Click here for comprehensive coverage of top Cities including Bengaluru, Delhi, Hyderabad, and more across India along with Stay informed on the latest happenings in World News.
SHARE THIS ARTICLE ON
Hindustantimes wants to start sending you push notifications. Click allow to subscribe