Dwarka expressway land mutation to be done this week: HSVP

The Haryana Shahari Vikas Pradhikaran(HSVP) expects to complete the much-delayed mutation process of an 18-km stretch in favour of the Gurugram Metropolitan Development Authority (GMDA) this week.

Published on: Sep 04, 2018 05:56 AM IST
Hindustan Times, Gurugram | By
Prefer HTon Google
Advertisement

Having cleared all legal and physical obstacles hindering the completion of Dwarka Expressway, the Haryana Shahari Vikas Pradhikaran (HSVP), formerly Huda, said it will complete the mutation process of an 18-km stretch in favour of the Gurugram Metropolitan Development Authority (GMDA) this week. After the mutation, i.e., getting names of the new owner changed in government records, for the stretch, a portion of it would then be handed over to the National Highways Authority of India (NHAI) for construction.

The Dwarka expressway  way was expected to be completed in 2010 but the project was delayed due to petitions and protests by land owners. (HT FILE PHOTO)
The Dwarka expressway way was expected to be completed in 2010 but the project was delayed due to petitions and protests by land owners. (HT FILE PHOTO)

“The GMDA would transfer the a 90-metre stretch to the NHAI for construction of the elevated stretch. The revenue officials have been asked to complete the transfer process,” HSVP administrator, Gurugram Chander Shekhar Khare said.

Once the land is mutated in favour of GMDA, the role of HSVP in the transfer of Dwarka Expressway would be over.

The HSVP is entitled to directly transfer land to the NHAI. “There are several formalities involved in this process including documentation, which is why it took time. However, the physical handover from one government agency to another can happen anytime,” Khare said.

The Expressway was expected to be completed in 2010 but the project was delayed due to petitions and protests by land owners, who demanded alternative plots and compensation.

The Expressway is going to run a length of 27km, connecting Shiv Murti near Mahipalpur on NH48 in Delhi to about 1km from the Kherki Daula toll plaza on the same road. The NHAI will build an eight-lane elevated road, underpasses at 10 points and four interchanges as part of the project.

 
ABOUT THE AUTHOR
Abhishek Behl

Abhishek Behl is principal correspondent, Hindustan Times in Gurgaon Bureau. He covers infrastructure, planning and civic agencies in the city. He has been covering Gurgaon as correspondent for the last 10 years, and has written extensively on the city.

Catch every big hit, every wicket with Crickit, a one stop destination for Live Scores, Match Stats, Infographics & much more. Explore now!.

Stay updated with all the Breaking News and Latest News from Mumbai. Click here for comprehensive coverage of top Cities including Bengaluru, Delhi, Hyderabad, and more across India along with Stay informed on the latest happenings in World News.
Catch every big hit, every wicket with Crickit, a one stop destination for Live Scores, Match Stats, Infographics & much more. Explore now!.

Stay updated with all the Breaking News and Latest News from Mumbai. Click here for comprehensive coverage of top Cities including Bengaluru, Delhi, Hyderabad, and more across India along with Stay informed on the latest happenings in World News.
SHARE THIS ARTICLE ON
Hindustantimes wants to start sending you push notifications. Click allow to subscribe