Next Story

Gurgaon: Power dept yet to decide on high tension wires, Iffco flyover work stuck

The NHAI needs these towers immediately removed for the construction to go forward. Work at the site has been stopped for the last couple of weeks.

Published on: Aug 05, 2017 10:29 PM IST
Hindustan Times | By , Gurgaon
Prefer HTon Google
Advertisement

For the National Highways Authority of India (NHAI), the presence of high tension electricity wires on the alignment of U-turn flyover and underpass coming up at Iffco Chowk is turning out to be major hurdle. The NHAI needs these towers immediately removed for the construction to go forward. Work at the site has been stopped for the last couple of weeks.

There are 12 such towers (electricity poles) to the left of the NH-8 near Iffco Chowk, if one is going from Delhi to Gurgaon. (Parveen Kumar/HT Photo)
There are 12 such towers (electricity poles) to the left of the NH-8 near Iffco Chowk, if one is going from Delhi to Gurgaon. (Parveen Kumar/HT Photo)

The Haryana Vidyut Prasaran Nigam (HVPN), the transmission agency that owns the high tension wires, once changed its plan again two days ago and wrote to the NHAI asking for a joint site inspection to explore the possibility of overhead replacement of wires.

Earlier, the plan was to construct an underground duct and shift the overhead cables into it. The NHAI, it is learnt, is unhappy with the change in the plan.

AK Sharma, project director, NHAI Gurgaon, said, “We have replied to HVPN stating our position about how the works are suffering due to the delay in shifting of high tension wires falling in the alignment of the flyover and underpass. HVPN was to give NHAI the approval for moving the overhead high tension wires underground. But now it says a fresh site inspection will be carried out to explore the option of overhead replacement.”

“The construction of the flyover is complete, except for the portion occupied by the power transmission towers. These towers are located along the Delhi Gurgaon Expressway – if one is going from Shankar Chowk to Iffco Chowk,” Sharma said.

There are 12 such towers (electricity poles) to the left of the NH-8 near Iffco Chowk, if one is going from Delhi to Gurgaon.

Anil Yadav, superintending engineer, HVPN, said, “There is no harm in exploring best the suitable option with regard to the high tension wires, but land limitation is a major constraint. There will be no delay as we will decide on this as soon we complete the site inspection with team of experts.”

 
ABOUT THE AUTHOR
Dhananjay Jha

Dhananjay Jha writes on development authorities, transport, industries, power and other developmental issues in Gurgaon. A journalist for over a decade, he has worked in Delhi and in HT’s Noida bureau.

Catch every big hit, every wicket with Crickit, a one stop destination for Live Scores, Match Stats, Infographics & much more. Explore now!.

Stay updated with all the Breaking News and Latest News from Mumbai. Click here for comprehensive coverage of top Cities including Bengaluru, Delhi, Hyderabad, and more across India along with Stay informed on the latest happenings in World News.
Catch every big hit, every wicket with Crickit, a one stop destination for Live Scores, Match Stats, Infographics & much more. Explore now!.