CAG questions land allotment to solar firms in Rajasthan districts

The Comptroller and Auditor General of India (CAG) has raised questions over the allotment of land to six solar companies for setting up solar thermal power plants (ST) in Jodhpur and Jaisalmer districts.

Published on: Dec 18, 2015, 14:36:04 IST
Hindustan Times | By , Jodhpur
Prefer HTon Google
Advertisement

The Comptroller and Auditor General of India (CAG) has raised questions over the allotment of land to six solar companies for setting up solar thermal power plants (ST) in Jodhpur and Jaisalmer districts.

According to the report, the Rajasthan state policy gave preferential treatment in the allotment of land to these developers as this land was allocated for public purpose. (Praful Gangurde/HT photo for representation)
According to the report, the Rajasthan state policy gave preferential treatment in the allotment of land to these developers as this land was allocated for public purpose. (Praful Gangurde/HT photo for representation)

The land was allotted to these companies for the Jawaharlal Nehru National Solar Mission (JNNSM) and migration scheme but these companies used the allotted land for developing their land bank.

The CAG report has recently been tabled in the Lok Sabha. According to the report, the Rajasthan state policy gave preferential treatment in the allotment of land to these developers as this land was allocated for public purpose. The preferential treatment included allocating government land at rates lower than the DLC rates and changing the land use status, the report mentioned.

The developers which have been flagged are Rajasthan Sun Technique Energy Pvt Ltd, M/s Corporate Ispat Alloys Ltd, M/s Diwakar Solar Projects Pvt Ltd, M/s KVK Energy Ventures Pvt Ltd, M/s Entegra Ltd and M/s Dalmia Solar Power Ltd.

The CAG also observed that in a demonstration programme in 2008, the state leased 375 acres of land to M/s Par Solar for five MW SPV plants, which were commissioned in March 2012. For the commissioning of one MW SPV project, approximately six acres of land was required.

CAG findings

According to CAG report which was recently tabled in the Lok Sabha, the allotted land was meant for public purpose.

The preferential treatment included allocating government land at rates lower than the DLC rates and changing the land use status, the report mentioned.

 