Mangrove cutting for sea link: SC sends petition back to HC

The HC, on February 8, had allowed Maharashtra State Road Development Corporation (MSRDC) — the agency implementing the rupees 11,332-crore project — to cut 1,585 mangrove trees on around 3 hectares. It was the final clearance MSRDC required to begin work on the project.

Published on: Apr 02, 2019 07:46 AM IST
Hindustan Times, Mumbai | By
Prefer HTon Google
Advertisement

The Supreme Court (SC) on Monday sent back the matter of felling mangrove trees for the Versova-Bandra Sea Link (VBSL) project to the Bombay high court (HC). The Apex Court was hearing a special leave petition filed by Khar resident and environmentalist Zoru Bhathena on March 25.

The Apex Court was hearing a special leave petition filed by Khar resident and environmentalist Zoru Bhathena on March 25. (HT PHOTO)
The Apex Court was hearing a special leave petition filed by Khar resident and environmentalist Zoru Bhathena on March 25. (HT PHOTO)

The HC, on February 8, had allowed Maharashtra State Road Development Corporation (MSRDC) — the agency implementing the rupees 11,332-crore project — to cut 1,585 mangrove trees on around 3 hectares. It was the final clearance MSRDC required to begin work on the project.

“The SC bench of justice Nageshwar Rao and justice MR Shah said how could the HC pass an order where 2.9907 hectare of mangroves can be permitted to be cut. The environment ministry’s CRZ permission in 2013 [for the project] was subject to only 150 square metres mangrove felling for a bridge to be built on stilts,” said Jatin Zaveri, counsel for the petitioner.

“We told the SC bench that the State Environment Impact Assessment Authority nod for the project mandated that no mangroves be destroyed. In such circumstances, MSRDC’s dem-and for 30,000 sqm of mangroves is unnecessary and akin to environmental destruction.”

“Based on this explanation, we got clearance from HC. We will explain the same [in HC] again.”

State government sources, who were involved in the clearance process, said the MSRDC proposal read that 2.9907 hectares of mangroves would be lost. “We do not decide how much mangrove area is lost. We only assess and ensure there is least possible damage,” said an official.

Bhathena, meanwhile, thanked the SC. “We are grateful the SC took note of our complaint, and allowed us to go back to HC to resolve the issue,” he said.

 
Catch every big hit, every wicket with Crickit, a one stop destination for Live Scores, Match Stats, Infographics & much more. Explore now!

Stay updated with all the Breaking News and Latest News from Mumbai. Click here for comprehensive coverage of top Cities including Bengaluru, Delhi, Hyderabad, and more across India along with Stay informed on the latest happenings in World News.
Catch every big hit, every wicket with Crickit, a one stop destination for Live Scores, Match Stats, Infographics & much more. Explore now!

Stay updated with all the Breaking News and Latest News from Mumbai. Click here for comprehensive coverage of top Cities including Bengaluru, Delhi, Hyderabad, and more across India along with Stay informed on the latest happenings in World News.
SHARE THIS ARTICLE ON
Hindustantimes wants to start sending you push notifications. Click allow to subscribe