BMC yet to get the show on the road

Long-drawn tendering processes, time-consuming procedures to get requisite clearances from traffic police and civic departments, and shoddy work by road contractors. Result: A rough ride and distressing monsoon for Mumbaiites every year, reports Poorvi Kulkarni.

Updated on: May 09, 2013 01:50 AM IST
Hindustan Times | By , Mumbai
Prefer HTon Google
Advertisement

Long-drawn tendering processes, time-consuming procedures to get requisite clearances from traffic police and civic departments, and shoddy work by road contractors. Result: A rough ride and distressing monsoon for Mumbaiites every year.

HT Image
HT Image

Ahead of this monsoon, the Brihanmumbai Municipal Corporation (BMC) had planned to utilise a hefty sum of Rs1,130 crore to carry out road-relaying work. However, the BMC is likely to end up using only half of this amount, thanks to a flawed, slow-paced bureaucratic system.

Although official figures on the extent of road work completed are yet to be released, senior civic officials said that only 50% of the work has been completed so far. On many of the 208 roads where resurfacing was planned in the island city and western suburbs, work has not even begun.

“While 50% of the work has been completed, 10-20% will be completed by May-end. Work on many roads is stuck as clearances from traffic police and other departments are pending,” said a senior civic official

Ashraf Azmi, Samajwadi Party corporator from Kurla, said: “Roads in eastern suburbs, especially in Kurla, are in a pitiable state. But, step-motherly treatment continues to be meted towards this region.”

Though the civic administration admitted that the deadline to complete the road works will not be met, it claimed that roads would be repaired by May-end. “In cases where roadwork cannot begin before monsoon, contractors will be given work orders and given the charge of maintaining roads during rains,” said Rajiv Jalota, additional municipal commissioner. He said preventive maint­enance of roads with bad patches will be taken up simultaneously. “The work will begin in three-four days.”

Why your rides may be bumpy this year too

 
Catch every big hit, every wicket with Crickit, a one stop destination for Live Scores, Match Stats, Infographics & much more. Explore now!

Stay updated with all the Breaking News and Latest News from Mumbai. Click here for comprehensive coverage of top Cities including Bengaluru, Delhi, Hyderabad, and more across India along with Stay informed on the latest happenings in World News.
Catch every big hit, every wicket with Crickit, a one stop destination for Live Scores, Match Stats, Infographics & much more. Explore now!

Stay updated with all the Breaking News and Latest News from Mumbai. Click here for comprehensive coverage of top Cities including Bengaluru, Delhi, Hyderabad, and more across India along with Stay informed on the latest happenings in World News.
SHARE THIS ARTICLE ON
Hindustantimes wants to start sending you push notifications. Click allow to subscribe