No official pact but Rs 18 cr paid

The Brihanmumbai Municipal Corporation (BMC) has started work to close the Deonar dumping ground and also paid the contractor Rs 18 crore without signing an official agreement with the company.

Updated on: Jul 05, 2010 12:41 AM IST
Hindustan Times | By , Mumbai
Prefer HTon Google
Advertisement

The Brihanmumbai Municipal Corporation (BMC) has started work to close the Deonar dumping ground and also paid the contractor Rs 18 crore without signing an official agreement with the company.

HT Image
HT Image

A query filed by Mulund resident Arun Kumar Gupta under the Right to Information (RTI) Act revealed that the concession agreement between the contractor and the BMC sanctioning the Rs 3,495-crore project is still being prepared although the contract period started in December. The contractor, meanwhile, was paid Rs 18 crore for five months for ‘receiving municipal solid waste’.

B.P. Patil, chief engineer, Solid Waste Management (SWM) confirmed that the agreement was not ready and that the contractor, United Phosphorus Limited (UPL), is yet to install a composting machine to process the waste. “They [UPL] are compacting the waste, ensuring there is no odour or fire. Processing will happen once the lease agreement is signed,” Patil said.

Patil said the contractor cannot import the composting machine without the land lease agreement, which the state is still studying.

A senior civic official said the BMC did not wait for the agreement to be signed because it was under pressure to start the project. “There was a contempt petition against us in the high court. So we had to start work immediately.”

Waste management experts are calling this a “waste of public money”. “Why pay them Rs 18 crore for doing what the BMC was already doing?” S.R. Maley, solid waste management expert and member of the high court committee on SWM, asked. Patil said the BMC had to pay UPL because it had started creating infrastructure on the site. The contractor gave the BMC a guarantee of only Rs 5 crore although the civic body had already paid more than thrice the amount.

The BMC’s decision to hand over the Deonar dumping ground for partial scientific closure in July 2009 had created a row with the Standing Committee initially rejecting the proposal for being too expensive.

 
Catch every big hit, every wicket with Crickit, a one stop destination for Live Scores, Match Stats, Infographics & much more. Explore now!

Stay updated with all the Breaking News and Latest News from Mumbai. Click here for comprehensive coverage of top Cities including Bengaluru, Delhi, Hyderabad, and more across India along with Stay informed on the latest happenings in World News.
Catch every big hit, every wicket with Crickit, a one stop destination for Live Scores, Match Stats, Infographics & much more. Explore now!

Stay updated with all the Breaking News and Latest News from Mumbai. Click here for comprehensive coverage of top Cities including Bengaluru, Delhi, Hyderabad, and more across India along with Stay informed on the latest happenings in World News.
SHARE THIS ARTICLE ON
Hindustantimes wants to start sending you push notifications. Click allow to subscribe