Delay in project completion akin to sedition: Madhya Pradesh govt
The Madhya Pradesh water resources department has blacklisted a Hyderabad-based company over a nine-year delay in completing a project, saying the losses caused by the firm to the country amounted to “sedition”, according to officials aware of the details.
The Madhya Pradesh water resources department has blacklisted a Hyderabad-based company over a nine-year delay in completing a project, saying the losses caused by the firm to the country amounted to “sedition”, according to officials aware of the details.

The company, HES Infra Pvt Limited, in 2013 had won the bid to build canals to irrigate 40,050 hectares in the command area of Tons river, for ₹238.33 crore. The work was to be completed in three years, the officials said.
The project remained incomplete till date, the officials said, prompting the state’s water resource department to blacklist the company on November 21.
HT tried to reach out to HES Infra Pvt Limited for a response but did not get one immediately.
In its blacklisting order, a copy of which HT has seen, the state government said the delay in work amounted to “sedition” as it caused a loss of ₹1,715 crore to the national agriculture production.
“The contracted work was not completed by the contractor even after more than nine years,” the order signed by Ganga Kachar water resource department, Rewa chief engineer C M Tripathi said.
“Against 40,050 hectares of land, the work of only 15,000 hectares of irrigation area has been developed by the contractor till date. Due to incomplete work of the main canal, its minor canals and concrete structures, the remaining 25,050 area is deprived of irrigation,” it added.
The company, which was issued a show cause notice on October 1, cited non-payment of dues, the Covid-19 pandemic and timely administrative approval for the delay, the order said.
“In its reply (on October 18), the contractor has mainly cited non-payment of dues, Covid-19 pandemic and lack of revised administrative approval as the reason for non-completion of the work. The arguments given by the contractor in his reply were fully examined and it was found that the work of land acquisition was to be done by the contractor as per provisions given in the contract, which was argued to be delayed due to Covid-19. It is not acceptable for the contractual completion date (was) September 2016 and Covid-19 pandemic (was) reported in 2020,” the order said.
“Over 25,000 hectares of land is still unirrigated due to delay in the project. According to the agriculture department, about 3.5 MT grains grow in every hectare and the total estimated cost of production in 25,000 hectare land in six years is ₹1,715 crore,” it added.
“It is an act of sedition. I have warned 14 companies with the same kind of notices because a case should be registered against these companies for causing loss to the nation,” he added.
The order said the company has been blacklisted for three years, which means it cannot participate in any government work either on its own or through its partners/operators.
ABOUT THE AUTHORShruti TomarI have spent over a decade chronicling Madhya Pradesh’s political and social landscape, covering politics, investigative journalism, crime, human interest, and government policy, blending sharp insight with ground‑level depth. I have closely tracked three assembly elections, three Lok Sabha elections, leadership transitions in MP while exposing governance lapses, tender irregularities, and flawed policy rollouts. My reports have revealed gaps in the Cheetah project, irregularities in medical education, rigging in recruitment exams, and loopholes in policy implementation. In crime reporting, I have moved beyond FIRs to map systemic patterns — from organised crime networks and gender‑based violence to custodial accountability — balancing urgency with sensitivity. My journalism is defined by a commitment to human interest. I have profiled the marginalised Bancchda community, documented atrocities against tribal groups, and highlighted efforts to preserve their culture through heritage liquor and revival of spiritual practices. I have reported on farmers struggling with failed MSP promises, giving voice to those often reduced to statistics in policy files. Passionate about field reporting, I have reported on rampant sand mining in Chambal and Narmada, pharmaceutical companies supplying medicines under altered names, the dire condition of schools and colleges, the plight of commercial sex workers, and skewed sex ratios in specific districts. Beyond deadlines, and as HT’s state correspondent and assistant editor in Madhya Pradesh, I engage with ministers, farmers, students, and activists, believing the best policy stories begin with a single human voice. A postgraduate in Journalism and Mass Communication, I also hold a diploma in sports journalism.Read More

E-Paper


