Steep slopes, location access: How Chenab railway project team tackled construction challenges

PM Narendra Modi on Friday inaugurated the Chenab Bridge, Anji Rail Bridge and Udhampur-Srinagar-Baramulla Rail Link (USBRL) project.

Updated on: Jun 07, 2025 01:02 PM IST
Advertisement

Chenab bridge, the world’s highest rail bridge was inaugurated by Prime Minister Narendra Modi on Friday. Behind the bridge that offers connectivity of Kashmir to the rest of India, was a construction team that faced several challenges. One of the main obstacles that they dealt with was how to reach the location surrounded by the steep slopes of Himalayas.

Temporary roads to access site

Afcons, the company that constructed Chenab bridge, said that one of the key challenge was to access the bridge location and to transport the equipments. (PTI)
Afcons, the company that constructed Chenab bridge, said that one of the key challenge was to access the bridge location and to transport the equipments. (PTI)

According to Afcons Infrastructure Limited, the company behind the making of the bridge, one of the key challenge was to access the bridge location and then to transport the equipments and construction material there. Initially they made use of mules and horses but over time temporary roads were made to access the site, said a spokesperson of the company. An 11- km road was constructed on the North side of the river bank and similarly a 12 km road was created on the South side. Executive Vice Chairman of Afcons, Krishnamurthy Subramanian highlighted the Chenab bridge in Jammu and Kashmir as a marvel of engineering and told PTI that it is a “symbol of India’s resolve to conquer most formidable challenges with ingenuity and courage.”

Specialised tools and machinery

To construct a viaduct, a structure designed to make roads and railways over rivers, was also a unique challenge. The company spokes person said, "There were multiple transition areas. Keeping this in mind, the launching sequence was meticulously planned in four sections," the spokesperson.

Also read: Chenab Rail Bridge to bring Delhi and Kashmir closer | Why is it important

Meanwhile the managing director of Afcons emphasised the importance of this project for the company saying, "For Afcons, it represents our unwavering commitment to nation-building and our ability to reimagine infrastructure in the toughest terrains.” He further said that this bridge will inspire generations of engineers about the power of Indian engineering.

Another key milestone was that for the first time in the Indian Railways' history, a laboratory accredited by the National Accreditation Board for Testing and Calibration (NABL) was set up to ensure the quality of the project.

(With PTI Inputs)

 
ABOUT THE AUTHOR
Akansha Purohit

Akansha Purohit is a Content Producer at Hindustan Times, where she is part of the online news desk. She began her journey with the organisation as an intern and later joined the newsroom in a full-time editorial role. With close to a year of experience at Hindustan Times, she contributes to the daily news cycle by writing, curating, and editing digital content. Her work primarily focuses on national and international news, along with explainers that simplify complex developments and ongoing issues. She also writes on matters of public interest, and handles blogs with live updates. Akansha holds a bachelor’s degree in Journalism from Kamala Nehru College, University of Delhi, and completed her postgraduate studies in Digital Media from the Indian Institute of Mass Communication (IIMC), Delhi. During her postgraduate programme, she worked on several research and journalism projects that strengthened her reporting, editing, and digital storytelling skills.

Check India news real-time updates, latest news on Hindustan Times and more across India.
Check India news real-time updates, latest news on Hindustan Times and more across India.
SHARE THIS ARTICLE ON
Hindustantimes wants to start sending you push notifications. Click allow to subscribe