Delhi Metro’s longest Pink Line to open in three phases by Sept 2017 | Latest News Delhi - Hindustan Times
close_game
close_game

Delhi Metro’s longest Pink Line to open in three phases by Sept 2017

Hindustan Times | By, New Delhi
Oct 21, 2016 02:13 PM IST

The longest corridor of Delhi Metro’s Phase 3 project, the Pink Line (Mukundpur-Shiv Vihar), will be opened in its entirety by September next year.

The longest corridor of Delhi Metro’s Phase 3 project, the Pink Line (Mukundpur-Shiv Vihar), will be opened in its entirety by September next year.

The Pink Line with 38 metro stations is the most significant corridor of the entire Delhi metro network as it has been laid like a ring touching all parts of Delhi.(HT file photo)
The Pink Line with 38 metro stations is the most significant corridor of the entire Delhi metro network as it has been laid like a ring touching all parts of Delhi.(HT file photo)

Launch of the 58.389 km-long line has been divided into three phases as the Delhi Metro Rail Corporation (DMRC) still hasn’t been able to acquire land at Trilokpuri and Hasanpur village in IP Extension.

Hindustan Times - your fastest source for breaking news! Read now.

“The issues we are facing are only on one side of the line — East Delhi. More than Trilokpuri, land hurdle at Hasanpur village is affecting us as it just cuts the line’s connectivity to the new Vinod Nagar depot. So, while we have the stretch from Shiv Vihar to Karkardooma ready, we can’t run it because we do not have anywhere to park our trains at night,” said Mangu Singh, managing director, DMRC.

The Mukundpur to Lajpat Nagar (18 stations) stretch on the line will be opened in June, followed by Lajpat Nagar to Mayur Vihar Pocket-1 (five stations) in July. The last stretch of 14 stations from Mayur Vihar Pocket-1 to Shiv Vihar will be launched in September.

The Pink Line with 38 metro stations is the most significant corridor of the entire Delhi metro network as it has been laid like a ring touching all parts of Delhi. With eight interchange stations the line alone is going to take the maximum load of the 40 lakh per day metro ridership which is expected after opening of Phase 3.

“Since we realised this matter is not going to be resolved soon, we have tweaked the entire plan now. There is going to be a good gap between the opening of the first and the last stretch. So, we have made new arrangements for reversal of trains at Mayur Vihar Pocket-1 station. Now all trains on the Pink Line will operate only through the Mukundpur depot until the entire line along with Vinod Nagar depot is opened,” explained Singh.

Read more: Delhi govt to relocate slum dwellers in E Delhi to widen Delhi-Meerut highway

The land acquisition hurdles at Punjabi Bagh and Mayapuri were resolved in July end this year. “We had planned accordingly and so physical work or installation of viaducts on the first two stretches will be over by December after which trial runs will begin,” he added.

Unveiling 'Elections 2024: The Big Picture', a fresh segment in HT's talk show 'The Interview with Kumkum Chadha', where leaders across the political spectrum discuss the upcoming general elections. Watch now!
SHARE THIS ARTICLE ON
Share this article
  • ABOUT THE AUTHOR
    author-default-90x90

    Sweta Goswami writes on politics, urban development, transportation, energy and social welfare. Based in Delhi, she tracks government policies and suggests corrections based on public feedback and on-ground implementation through her reports. She has also covered the Aam Aadmi Party (AAP) since its inception.

SHARE
Story Saved
Live Score
OPEN APP
Saved Articles
Following
My Reads
Sign out
New Delhi 0C
Tuesday, March 19, 2024
Start 14 Days Free Trial Subscribe Now
Follow Us On