Revised seismic norms prompt GMRL to redesign Gurugram Metro structures

Metro officials said designs for piles, pillars and stations are being updated to meet specifications under the new seismic zone notification issued by BIS.

Published on: Feb 12, 2026, 04:24:08 IST
By , Gurugram
Share
Share via
  • facebook
  • twitter
  • linkedin
  • whatsapp
Copy link
  • copy link

Changes in India’s seismic design standards notified by the Bureau of Indian Standards (BIS) in November last year have prompted Gurugram Metro Rail Limited (GMRL) to revise the structural design of the entire Gurugram metro alignment, with stronger safety measures being incorporated into piles, pillars and stations, officials said.

The metro corporation said that they are taking steps to ensure the timelines are not impacted for the first phase.
The metro corporation said that they are taking steps to ensure the timelines are not impacted for the first phase.

Metro officials said designs for piles, pillars and stations are being updated to meet specifications under the new seismic zone notification issued by BIS. Additional designers and planners have been deployed to rework structural designs, though officials said efforts are being made to ensure the revisions do not affect construction timelines.

As per GMRL officials, the cost of revision in design is being estimated but it won’t have any significant increase in the project cost as the construction has just started. The metro corporation said that they are taking steps to ensure the timelines are not impacted for the first phase. Only structural design needs to be revised, they added.

According to the revised seismic design standard IS 1893 (Part 1):2025 and Part 5:2025 issued on November 3, 2025, most new projects are expected to be designed to zone five safety levels, even though the region remains officially in zone four. Experts said the norms require stronger reinforcement and ductile detailing, thicker structural walls, stiffer frames and deeper, more resilient foundations. The updated code replaces the 2016 version and is mandatory for all new construction nationwide, including Delhi NCR.

A senior GMRL official said the structural design of pillars, piles, spans and other components is being updated to meet zone five specifications. “Our job has become difficult and more time taking as all structures are being redesigned. The design softwares earlier were using seismic zone four specifications as base but now these are being updated. The design will ensure that the structures will be more resilient and tolerate stronger earthquakes,” the official said, adding that the revised parameters will be incorporated into the phase two tender.

An official of Systra, the design consultant for the metro, confirmed the changes. “This means deeper deeper bores, heavier reinforcement and more strength in the structures. This will cost more time and resources but the structures will be ready to to meet any eventuality,” he said.

Yogesh Bhasin, president, Structures. Signature Global, said the revised zoning effectively requires Delhi NCR to meet zone five specifications. “In seismic-prone regions like Delhi-NCR better design of structures, introducing vibrant control equipment, better reinforcement was key for safety. Meeting zone five parameters meeans we are ready for earthquakes measuring 7 on the richter scale. Doing it in the metro project at the design stage is a positive step,” he said.

Naveet Kour, scientist at Central Road Research Institute, said adopting the new code will improve earthquake safety. “Delhi NCR is practically in Zone five seismic category and the construction practices will have to be followed as per the new design code,” she said.

  • Abhishek Behl
    ABOUT THE AUTHOR
    Abhishek Behl

    Abhishek Behl is a Special Correspondent with Hindustan Times, Gurugram bureau. With over a decade of experience in journalism, he reports on Gurugram's rapid urban transformation, covering the city's changing infrastructure, governance, and planning landscape. His reporting spans major civic agencies, such as the Gurugram Metropolitan Development Authority (GMDA), Department of Town and Country Planning (DTCP), Haryana Shahari Vikas Pradhikaran (HSVP), and the National Highways Authority of India (NHAI). Behl has reported on key urban development issues such as RRTS projects, metro expansion, road and highway projects, water supply, drainage, mobility, environmental concerns, land use planning, affordable housing, and the city's real estate sector. He closely tracks policy decisions, infrastructure implementation, and their impact on the city and its residents. He also covers regulatory action against illegal constructions, urban flooding, traffic management, and initiatives aimed at improving civic services and sustainable development. Behl has also written on political developments in south Haryana, focusing on elections and governance. His journalism is driven by fact-based reporting, ground-level coverage, and an understanding of the social and economic dynamics of Gurugram. Apart from work he is a cyclist and a cricketer and a resident of Palam Vihar since 2010.Read More

Catch every big hit, every wicket with Crickit, a one stop destination for Live Scores, Match Stats, Infographics & much more. Explore now!.

Stay updated with all the Breaking News and Latest News from Mumbai. Click here for comprehensive coverage of top Cities including Bengaluru, Delhi, Hyderabad, and more across India along with Stay informed on the latest happenings in World News.