The government on Tuesday said that of the 631 projects, costing Rs 100 crore and above, as many as 327 delayed ones reported a total cost overrun of Rs 52,213 crore till March end this year.

The cost over runs are due to escalation and other factors, including delays in projects for various reasons, change in scope and increase in quantities, Minister of State for Statistics and Programme Implementation Sriprakash Jaiswal said in a written reply in the Rajya Sabha.
The cost overrun of these projects is 15.8 per cent of their original approved costs, the statement said.
The number of such projects were 285 till March 31, 2004. Out of this, as many as 118 projected a cost escalation of Rs 28,472.6 crore till March end in 2004, which was 52 per cent of their approved original costs.
Stay updated with all top Cities including, Bengaluru, Delhi, Mumbai and more across India. Stay informed on the latest happenings in World News along with Delhi Election 2025 and Delhi Election Result 2025 Live, New Delhi Election Result Live, Kalkaji Election Result Live at Hindustan Times.
Stay updated with all top Cities including, Bengaluru, Delhi, Mumbai and more across India. Stay informed on the latest happenings in World News along with Delhi Election 2025 and Delhi Election Result 2025 Live, New Delhi Election Result Live, Kalkaji Election Result Live at Hindustan Times.