Sign in

CWG overlays equipment cost 1,400% more: CVC

Officials of the Commonwealth Games Organising Committee had hired equipment for overlay works at over 14 times the actual price, a CVC investigation has found.

Updated on: Mar 13, 2011, 15:45:28 IST
PTI | By , New Delhi
Share
Share via
  • facebook
  • twitter
  • linkedin
  • whatsapp
Copy link
  • copy link

Officials of Commonwealth Games Organising Committee had hired equipment for overlay works at over 14 times the actual price, a CVC investigation has found.

HT Image
HT Image

The CVC, in its report to CBI on overlays scam, has said that the committee had taken equipment on rent at an inflated Rs 42.34 crore (over 1,400% higher) against the actual cost of Rs 2.80 crore, thus giving undue benefits to the companies.

Besides, the investigators of the anti corruption watchdog have found indications of collusive bidding, cost of renting items far higher than the cost of procurement, unreasonably high rate on supplied items, double payment and inferior quality in the overlays work.

The OC had given an overlays contract of Rs 687.86 crore to four firms; M/s Pico Deepali Overlays Consortium, Delhi, M/s Nussli (Switzerland) Ltd, Switzerland, M/s ESAJV:D Art:Indo Consortium, New Delhi and M/s GL-Meroform, France.

The work included managing temporary structures like tents, video boards, furnitures, fixtures, generator sets, among others, at 62 venues (23 competition venues, 32 training venues and 7 non competition venues) grouped in seven clusters.

In its internal report, a copy of which is available with PTI, the CVC also said there was "no cooperation" from OC officials in furnishing documents, clarifications and information during its probe in the alleged scam.

"Instead of furnishing specific replies to the queries...they (OC) have sent voluminous documents without indicating their relevance. Site visits were futile as no document was available, and none of the officials available at site could explain the detailed methodology for verification and recording of measurements of supply, installation, testing and commissioning of various items of the overlays work," the report said.

It said, initially, a tentative estimate of Rs 400 crore on account of overlays had been made. Subsequently, a cost estimate of Rs 948.52 crore was prepared by the OC. This was brought down to Rs 687.86 crore (including Rs 58.90 crore for Image and Look, Rs 54 crore for TSR and network switches etc, and Rs 40 crore for contingencies).

Officials of the probity watchdog found that there were discrepancies in choosing the companies for awarding works. Some of the companies did not meet pre-qualification criteria.

Citing indication of collusion bidding, the report said, "Bidders were asked to submit cluster-wise prices. Bidders have quoted different prices for different clusters for the same items."

Catch every big hit, every wicket with Crickit, a one stop destination for Live Scores, Match Stats, Infographics & much more. Explore now!

Stay updated with all top Cities including, Bengaluru, Delhi, Mumbai and more across India. Stay informed on the latest happenings in World News along with Delhi Election 2025 and Delhi Election Result 2025 Live, New Delhi Election Result Live, Kalkaji Election Result Live at Hindustan Times.