The Delhi Metro Rail Corporation plans to construct nine power-receiving sub-stations and strengthen four of its existing sub-stations to power the Metro corridors that are coming up as part of its Phase 3 of expansions.

The Delhi Metro’s power requirements are currently regulated by 15 sub-stations, which are located in different parts of the National Capital Region.
Of the new sub-stations, five — Yamuna Vihar, Vinod Nagar depot, INA, Dhaula Kuan and Mukundpur Depot — will cater to the 56km-long Mukundpur-Gokulpuri (Yamuna Vihar) corridor. Three sub-stations — Kalkaji, RK Puram and Palam — will supply to the 34km-long Janakpuri West-Botanical Garden corridor. A new sub-station at Faridabad will supply power to the 14km-long Badarpur-YMCA Chowk corridor.
However, power to the 3km-long Jahangirpuri-Badli corridor, which will be an extension of the Gurgaon-Jahangirpuri line, would be supplied by existing sub-stations.
“Auxiliary power at 33KV and traction power at 25KV will be supplied from these receiving sub-stations to the new Metro stations,” DMRC spokesperson Anuj Dayal said.
The sub-stations at Jahangirpuri, Subhash Nagar, Botanical Garden and Kashmere Gate will be augmented so that their feeds can be extended to Phase 3 corridors.
{{/usCountry}}The sub-stations at Jahangirpuri, Subhash Nagar, Botanical Garden and Kashmere Gate will be augmented so that their feeds can be extended to Phase 3 corridors.
{{/usCountry}}Stay updated with all top Cities including, Bengaluru, Delhi, Mumbai and more across India. Stay informed on the latest happenings in World News along with Delhi Election 2025 and Delhi Election Result 2025 Live, New Delhi Election Result Live, Kalkaji Election Result Live at Hindustan Times.
Stay updated with all top Cities including, Bengaluru, Delhi, Mumbai and more across India. Stay informed on the latest happenings in World News along with Delhi Election 2025 and Delhi Election Result 2025 Live, New Delhi Election Result Live, Kalkaji Election Result Live at Hindustan Times.