...
...
Next Story

One year later, BRT stuck in same jam

A near-empty bus lane, a long queue of cars, autos and two-wheelers in the motor vehicle lane and pedestrians jumping over the iron railings—nothing much seems to have changed in the past one year since Delhi's first Bus Rapid Transit (BRT) was opened for trial run.

Updated on: Apr 21, 2009 12:22 AM IST
Hindustan Times | By , New Delhi
Prefer HTon Google
Advertisement

A near-empty bus lane, a long queue of cars, autos and two-wheelers in the motor vehicle lane and pedestrians jumping over the iron railings—nothing much seems to have changed in the past one year since Delhi's first Bus Rapid Transit (BRT) was opened for trial run.

HT Image
HT Image

The only visible change is that the number of cars and two-wheelers jumping over to the bus lane has come down. Instead of honking at vehicles ahead, motorists now switch off the engine of their vehicles at busy intersections, seemingly reconciled to the fact that they cannot speed on this 5.8-kilometre stretch, between Dr Ambedkar Nagar and Moolchand
hospital, as they would a year ago during the non-peak hours.

After receiving flak from the public as well as transport experts, the Delhi Government had come up with proposals to streamline traffic flow and improve pedestrian movement on BRT corridor. Proposals included construction of foot overbridges at points where pedestrian movement is heavy, construction of a parallel road, which could take vehicular load off the corridor and installing intelligent traffic system (ITS) for better flow of vehicles.

“Approvals take time to come in. Both the DDA technical committee and United Traffic and Transport Infrastructure Centre have approved the design of the parallel road and we expect approval from the DUAC soon. We have also finalised the tender for ITS system,” transport commissioner R.K.Verma said.

Officials insist traffic movement has improved on the corridor since its first trial run.

“The speed of buses has gone up by 19 per cent. Throughput of vehicles at all intersections has also improved. With the construction of parallel road, which should take about 7-8 months, 2 more lanes will be available to motorists. There has been no accident on this stretch in the past eight months," said Delhi chief secretary Rakesh Mehta, adding police has been told to clear encroachment from cycle and pedestrian lane.

 
Catch every big hit, every wicket with Crickit, a one stop destination for Live Scores, Match Stats, Infographics & much more. Explore now!

Stay updated with all top Cities including, Bengaluru, Delhi, Mumbai and more across India. Stay informed on the latest happenings in World News along with Delhi Election 2025 and Delhi Election Result 2025 Live, New Delhi Election Result Live, Kalkaji Election Result Live at Hindustan Times.
Catch every big hit, every wicket with Crickit, a one stop destination for Live Scores, Match Stats, Infographics & much more. Explore now!

Stay updated with all top Cities including, Bengaluru, Delhi, Mumbai and more across India. Stay informed on the latest happenings in World News along with Delhi Election 2025 and Delhi Election Result 2025 Live, New Delhi Election Result Live, Kalkaji Election Result Live at Hindustan Times.
SHARE THIS ARTICLE ON
Hindustantimes wants to start sending you push notifications. Click allow to subscribe