Fly ash utilisation deadline extended for thermal power plants

ByJayashree Nandi
Apr 26, 2021 05:04 PM IST

The new draft notification also gives 10 years to thermal power plants to utilise fly ash or legacy ash which is stored. For the first time, the notification has a provision of imposing fines on thermal power plants that don’t comply with the new timeline

The Union environment ministry has extended the deadline for thermal power plants to ensure 100% utilisation of fly ash by 3 to 5 years, according to a new draft notification issued by the ministry on April 22.

Representational Image. (File photo)
Representational Image. (File photo)

It also gives 10 years to thermal power plants to utilise the unutilised fly ash, or legacy ash which is stored. For the first time, the notification has a provision of imposing fines on thermal power plants that don’t comply with the new timelines.

Hindustan Times - your fastest source for breaking news! Read now.

The previous deadline for 100% fly ash utilisation was December 31, 2017, as per a notification issued by the ministry on January 25, 2016. As per the new draft notification, thermal power plants (TPP) with fly ash utilisation of 60% to 80% will get 4 years while those with fly ash utilisation of less than 60% will get 5 years’ time to ensure 100% fly ash utilisation.

Non-compliant power plants will be slapped a fine of 1,000 per tonne on unutilised ash during the end of the deadline. Coal or lignite plants which are not able to utilise 100% of ash in the third year of the next three-year cycle, would be liable to pay a fine of 1,000 per tonne on the unutilised quantity.

For legacy ash, if the coal- or lignite-based thermal power plant has not achieved utilisation equivalent of at least 20% (in the first year), 35% (in the second year), 50% (from third to tenth year) as stipulated in the notification, a fine of 1,000 per tonne of unutilised legacy ash during that financial year will be imposed. And, if the utilisation of legacy ash is not completed at the end of 10 years, a fine of 1,000 per tonne will be imposed on the remaining unutilised quantity.

Also Read | Earth Day: A reminder there’s no plan(et) B

“The new deadlines have been decided based on the current utilisation of fly ash at thermal power plants. The provision of fines has been made under the ‘polluter pays’ principle,” said a senior environment ministry official.

“The fine collected by Central Pollution Control Board (CPCB) from the thermal power plants and other defaulters shall be used towards the safe disposal of the unutilised ash. The liability of ash utilisation shall be with TPPs even after imposition of fines on unutilised quantities,” the notification states.

Ash generated from thermal power plants can be utilised for manufacturing brick /blocks/tiles; cement manufacturing, ready mix concrete; construction of road and fly over embankment; ash and geo-polymer-based construction material; construction of dam; filling up of low lying areas; filling of mine voids; manufacturing of sintered/ cold bonded ash aggregate etc.

All agencies (government, semi government and private) engaged in construction activities such as road laying, road and flyover embankments, shoreline protection structures in coastal districts and dams within 300 km from the lignite/coal-based TPPs shall mandatorily utilise fly ash, provided it is delivered at the project site free of cost and transportation cost is borne by the thermal power plants. Thermal power plants may charge for ash cost and transportation as per mutually agreed terms, in case the plant is able to dispose the ash through other means and agencies make request to procure it.

Also Read | 8 states most prone to climate crisis: Study

“This notification is the most elaborate than any previous fly ash utilisation notifications that have been in place since the late 1990s in that it acknowledges legacy problems of fly ash non-utilisation and introduces fines for non-compliance. But it also falls short on some significant questions. Fly ash management is a financial problem for generators of fly ash which is what leads to indiscriminate dumping. It is also a result of hiding the amount of ash that will be generated by making operations appear acceptable while seeking pollution consents and environmental approvals. In places where ash dykes routinely leak, pipelines regularly burst, and fly ash is habitually dumped indiscriminately, impacts of fly ash are not only about technical compliance. It is a reality that affects ecology, public health and food security,” said Kanchi Kohli, legal researcher at Centre for Policy Research.

The environment ministry had last month issued new norms which give an extension of 1 to 3 years to all thermal power plants to comply with the emission norms. A Centre for Science and Environment (CSE) analysis had found that the penalty charged to companies for not complying with the extended deadline is lower than the cost of complying. CSE’s analysis showed that while installing the equipment for pollution control would cost between 40-100 lakh/MW, the penalty that thermal power plants would have to pay to keep running without installing the equipment is only 5-11 lakh/MW as per the new amendment.

Unveiling Elections 2024: The Big Picture', a fresh segment in HT's talk show 'The Interview with Kumkum Chadha', where leaders across the political spectrum discuss the upcoming general elections. Watch now!

Get Current Updates on India News, Election 2024, Arvind Kejriwal News Live, Bihar Board 10th Result 2024 Live along with Latest News and Top Headlines from India and around the world.
SHARE THIS ARTICLE ON
Share this article
SHARE
Story Saved
Live Score
OPEN APP
Saved Articles
Following
My Reads
Sign out
New Delhi 0C
Friday, March 29, 2024
Start 14 Days Free Trial Subscribe Now
Follow Us On