Sikkim expected to get rail connectivity by 2023: official

An official from the Indian Railway Construction Company, which is implementing the project, said that 30% of the work has been completed
SWhile 41.54 km of the railway line falls in the Darjeeling and Kalimpong districts of West Bengal, the remaining portion of around 3.44 km will run through Sikkim (HT Photo/representative use)
SWhile 41.54 km of the railway line falls in the Darjeeling and Kalimpong districts of West Bengal, the remaining portion of around 3.44 km will run through Sikkim (HT Photo/representative use)
Published on Nov 15, 2021 10:35 AM IST
Copy Link

Sikkim is expected to get rail connectivity with the rest of India by 2023 as the 44.98-km long Sevoke-Rangpo railway line is set to become operational within two years, an official has said.

“The Sevoke-Rangpo rail line would become operational from 2023,” said Anshul Gupta, the general manager of the North-East Frontier Railway, after visiting the project site at Sevoke, around 20 km from Siliguri in West Bengal. “Despite the difficult terrain, land-related hiccups, and very difficult land strata, the project would be completed in 2023.”

Then railway minister Mamata Banerjee laid the foundation stone for the project in 2009 and the project was supposed to be completed by 2015.

Railway officials said that the Prime Minister’s office and the Railway Board have set December 2023 as the project completion target.

An official from the Indian Railway Construction Company, which is implementing the project, said that 30% of the work has been completed.

Also Read: NIT Sikkim’s permanent campus to be ready within next 3 years: MoS Education

The line, which will connect West Bengal and Sikkim, was estimated to be completed at the cost of 1,339.48 crore. But because of the delay in the construction, the cost has escalated to more than 5,000 crore.

While 41.54 km of the railway line falls in the Darjeeling and Kalimpong districts of West Bengal, the remaining portion of around 3.44 km will run through Sikkim.

The project includes 14 tunnels, 17 bridges, and five stations, which include one at Teesta in Kalimpong district that would be underground. At least 86% of the route will pass through 14 tunnels out of which 13 tunnels are in West Bengal.

SHARE THIS ARTICLE ON
  • ABOUT THE AUTHOR

    I am working with Hindustan Times since 2001 and am posted in Siliguri, West Bengal, as Principal Correspondent. I have been regularly covering vast area of northern parts of West Bengal, Sikkim and parts of Nepal and Bhutan.