The Bhakra Beas Management Board (BBMB) has surpassed the energy generation target set by the Central Electricity Authority (CEA) for 2013-14 in the first nine months itself.

chandigarh Updated: Jan 06, 2014 21:21 IST
HT Correspondent
HT Correspondent
Hindustan Times

The Bhakra Beas Management Board (BBMB) has surpassed the energy generation target set by the Central Electricity Authority (CEA) for 2013-14 in the first nine months itself.


The BBMB generated 9,679 million units (MUs) from April 1 to December 21, 2013, against the full-year target of 9,665 MUs.

According to the BBMB spokesman, this was facilitated by ensuring high machine availability of 95.08% as well as optimal water reservoir operations, leading to effective utilisation of inflows.