WR likely to clear Elphinstone Bridge demolition next week

Published on: Nov 15, 2025 05:12 am IST

A team comprising WR and MRIDC officials visited the demolition site on Friday afternoon as part of preparatory works to dismantle the western side of the bridge, which falls under WR’s jurisdiction.

Mumbai: The demolition of the remaining portion of the British-era Elphinstone Bridge may finally begin next week, with Western Railway (WR) expected to give a go-ahead despite its ongoing dispute with the Maharashtra Rail Infrastructure Development Corporation (MRIDC) over way-leave charges, officials said.

Mumbai, India. Nov 04, 2025 - The 112-year-old Elphinstone Bridge was closed to vehicle traffic on September 12. Its approach roads were demolished over the past seven weeks, leaving only a 132-metre stretch that runs above the railway tracks. Mumbai, India. Nov 04, 2025. (Photo by Raju Shinde/HT Photo) (Raju Shinde)
Mumbai, India. Nov 04, 2025 - The 112-year-old Elphinstone Bridge was closed to vehicle traffic on September 12. Its approach roads were demolished over the past seven weeks, leaving only a 132-metre stretch that runs above the railway tracks. Mumbai, India. Nov 04, 2025. (Photo by Raju Shinde/HT Photo) (Raju Shinde)

A team comprising WR and MRIDC officials visited the demolition site on Friday afternoon as part of preparatory works to dismantle the western side of the bridge, which falls under WR’s jurisdiction.

The 112-year-old bridge was shut to traffic on September 12, after which its approach roads were razed. With the debris now cleared, cranes can be deployed to dismantle the remaining 132-metre stretch that passes above the railway tracks.

However, as HT reported in October, this work has been stalled due to MRIDC and WR being at loggerheads over way-leave charges—fees for using railway land—for demolishing the bridge and building the Sewri-Worli Elevated Corridor. While Central Railway (CR) had sought 10 crore as way-leave charges, WR demanded a significantly higher 59.14 crore.

While negotiations continued, MRIDC began demolishing the eastern side of the bridge, which falls under CR’s jurisdiction. However, WR is expected to give its nod soon, officials said.

“We are in the final stages of processing their request. Notwithstanding the difference of opinion on way-leave charges, we are likely to issue a go-ahead sometime next week,” a senior WR official, requesting anonymity. “A consensus can be arrived at on the amount even as the works are underway. This will not affect the project’s timelines.”

MRIDC’s spokesperson said that demolition has commenced from the eastern side of the bridge and will progress as planned.

Meanwhile, a team from VJTI has been appointed to monitor the structural health of the buildings near the site. On Friday, the team installed equipment to study the effect of vibrations on the buildings, a day after residents flagged concerns. As a preventive measures during pile boring, the VJTI team advised the contractor to reduce the RPM of the rig machine while socketing in hard rock, keep noise level low while removing mud from the auger and monitor vibration during pile boring.

The Elphinstone Bridge, which linked the congested Parel and Prabhadevi areas in central Mumbai, is being razed to make way for the Sewri-Worli Elevated Corridor, a key east-west connector being built by the Mumbai Metropolitan Region Development Authority (MMRDA). MRIDC, a joint venture between the Maharashtra government and the Ministry of Railways, is responsible for demolishing and rebuilding the section of the bridge passing over the railway lines.

The demolition of this section will require 78 rail blocks of four hours each, according to officials. The extent of disruption to suburban and long-distance rail services has not yet been announced.

The bridge will be replaced by a double-decker structure that will be a part of the upcoming 4.5-km Sewri-Worli Elevated Corridor. The lower deck will feature four lanes, two in each direction, connecting Senapati Bapat Road in the west and Dr Babasaheb Ambedkar Road in the east, along with a pavement for pedestrians. The upper deck will also have four lanes, two in each direction, connecting the Bandra-Worli Sea Link with the Mumbai Trans Harbour Link (Atal Setu).

An open web girder design has been finalised for the railway portion, whose reconstruction is estimated to cost 167.35 crore. The overall Sewri-Worli Elevated Corridor project is budgeted at 1,286 crore, and slated for completion by December 2026.

Catch every big hit, every wicket with Crickit, a one stop destination for Live Scores, Match Stats, Infographics & much more. Explore now!

Stay updated with all the Breaking News and Latest News from Mumbai. Click here for comprehensive coverage of top Cities including Bengaluru, Delhi, Hyderabad, and more across India along with Stay informed on the latest happenings in World News.
Catch every big hit, every wicket with Crickit, a one stop destination for Live Scores, Match Stats, Infographics & much more. Explore now!

Stay updated with all the Breaking News and Latest News from Mumbai. Click here for comprehensive coverage of top Cities including Bengaluru, Delhi, Hyderabad, and more across India along with Stay informed on the latest happenings in World News.
SHARE THIS ARTICLE ON
SHARE
close
Story Saved
Live Score
Saved Articles
Following
My Reads
Sign out
Get App
crown-icon
Subscribe Now!
AI Summary AI Summary

The demolition of Mumbai's Elphinstone Bridge is set to commence next week, pending approval from the Western Railway, despite disputes over way-leave charges with the Maharashtra Rail Infrastructure Development Corporation. The bridge, closed since September, will be replaced by a double-decker structure as part of the Sewri-Worli Elevated Corridor, projected to finish by December 2026.