Maha-Metro completes rly line crossing work at Pune in 5 hrs

After getting a five-hour mega block from railways, Maha-Metro completes the elevated metro corridor work, crossing two railway lines, at Khadki in Pune

Published on: Mar 12, 2022, 24:00:00 IST
Share
Share via
  • facebook
  • twitter
  • linkedin
  • whatsapp
Copy link
  • copy link

PUNE: After getting a five-hour mega block from railways, Maha-Metro completed the elevated metro corridor work, crossing two railway lines, at Khadki.

After getting a five-hour mega block from railways, Maha-Metro completed the elevated metro corridor work, crossing two railway lines, at Pune (HT)
After getting a five-hour mega block from railways, Maha-Metro completed the elevated metro corridor work, crossing two railway lines, at Pune (HT)

Maha Metro Maharashtra Metro Rail Corporation (Maha-Metro) successfully finished the work within the allocated time.

Maha-Metro public relations officer Hemant Sonawane said, “Central railway had given us time between 11am and 4pm on Friday, and our team finished the work within deadline.”

Maha-Metro erected 79-metre-long girder crossing the railway lines using 30,000 bolts. The PCMC to Swargate metro corridor is elevated from PCMC to Range Hills and later goes underground from Agriculture College.