Mumbai-Ahmedabad bullet train project: 250 km pier, 100 km viaduct construction completed

Nov 24, 2023 04:18 PM IST

The milestone of constructing 100 km of viaducts has been achieved through launching 40-metre long 'full span box girders' and ‘segmental girders’.

The National High Speed Rail Corporation Limited (NHSRCL), overseeing the Mumbai-Ahmedabad bullet train corridor project, shared an update on Thursday saying that 100 km of viaducts and 230 km of pier work was completed for the corridor.

Works of first river bridge on bullet train corridor gain momentum
Works of first river bridge on bullet train corridor gain momentum

The milestone of constructing 100 km of viaducts has been achieved through launching 40-metre long 'full span box girders' and 'segmental girders', the NHSRCL has said.

Now catch your favourite game on Crickit. Anytime Anywhere. Find out how

Union railway minister Ashwini Vaishnaw shared a video of the project on his X (formerly Twitter) platform to give information about the accomplishment. "Progress of Bullet Train project: Till date: 21.11.2023Pillars: 251.40 KmElevated super-structure: 103.24 Km," Vaishnaw said in a post on X.

According to the corporation, the viaducts include bridges over six rivers flowing through Gujarat, namely Par and Auranga in Valsad, Purna, Mindhola, Ambika and Venganiya rivers in Navsari district.

"The first girder of the project was launched on November 25, 2021, while the first km of viaduct was ready in six months on June 30, 2022. It achieved construction of 50 km of viaduct on April 22, 2023 and, thereafter, in six months 100 km of viaduct were completed," the NHSRCL said.

"The Full Span Launching technique (FSLM), where 40-metre long box girders are launched by state-of-the-art equipment, is being used along with span by span launching of segments. FSLM is 10 times faster than the span by span method, which is normally used to build metro viaducts," it further added.

The installation of noise barriers has also started on the constructed viaduct, NHSRCL said in an official communication.

The laying of the first Reinforced Concrete (RC) track bed for the MAHSR corridor track system as used in Japanese Shinkansen has also started in Surat. This is for the first time, the J-slab ballastless track system is being used in India, NHSRCL said.

Further, the breakthrough of the first mountain tunnel of 350 m has been completed in Valsad while the first steel bridge of 70 metres length has been erected in Surat. This is the first of the 28 steel bridges which will be the part of MAHSR corridor, it added.

The Mumbai-Ahmedabad High Speed Rail Corridor project, being developed at the cost of 1.08 lakh crore, was launched by PM Narendra Modi and his then-Japanese counterpart Shinzo Abe in September 2017.

As per the shareholding pattern, the central government will pay 10,000 crore to the NHSRCL, while Gujarat and Maharashtra are to pay 5,000 crore each. The rest of the cost is by way of a loan at 0.1 per cent interest from Japan.

(With inputs from agencies)

Get World Cup ready with Crickit! From live scores to match stats, catch all the action here. Explore now!

See more

Get Current Updates on India News, Budget 2024, Weather Today along with Latest News and Top Headlines from India and around the world.

SHARE THIS ARTICLE ON
Share this article
SHARE
Story Saved
Live Score
OPEN APP
Saved Articles
Following
My Reads
Sign out
New Delhi 0C
Thursday, June 20, 2024
Start 14 Days Free Trial Subscribe Now
Follow Us On