BMC fines GMLR flyover contractor ₹2.09 crore as delays push deadlines by nearly a year

BMC fines contractor S P Singla ₹2.09 crore for delays in Goregaon–Mulund Link Road, pushing completion to May 2026. Safety concerns raised by MLA.

Published on: Dec 8, 2025, 05:58:18 IST
Share
Share via
  • facebook
  • twitter
  • linkedin
Copy link
  • copy link

MUMBAI: The Brihanmumbai Municipal Corporation (BMC) has imposed a penalty of over ₹2.09 crore on contractor S P Singla for delays in Phase 3 of the Goregaon–Mulund Link Road (GMLR) project, pushing the project by almost a year.

Photo for representational purposes only (Pixabay)
Photo for representational purposes only (Pixabay)

The six-lane Singla flyover at the Goregaon (west-bound) end, originally scheduled for completion in July 2025, is now expected to open only in May 2026. On the Mulund side, only one arm of the six-lane flyover will be opened to the public on May 31, 2026, with the remaining portion requiring “a few more months,” officials said.

Together with the rotary and the upcoming cable-stayed bridge, the combined cost of the two major flyovers stands at ₹713 crore.

A senior bridges department official said the penalty for July and August delays was recovered on November 19. “The Goregaon side has missed the June 2025 deadline. Work on the Mulund side is progressing, but only one arm can open in May 2026.”

The Mulund end has been held up due to utilities, water pipelines and encroachment pockets near Sonapur junction, the official added. The original plan was to open the full Mulund flyover by May 31, 2026.

Additional municipal commissioner (projects) Abhijeet Bangar confirmed further action if delays persist. “We imposed a ₹2 crore penalty for missing deadlines. More penalties will follow if the contractor does not expedite work,” he said.

Of the 31 pillars required for the Goregaon side, 27 have been completed, with work on the remaining four underway. The structure will feature walkways on both sides, deck slabs, a 24.2-metre carriageway, two foot overbridges, and an elevated rotary at Mulund with three arms, towards Bhandup Complex, Guru Gobind Singh Road and the main flyover. A vehicular underpass at Mulund is already operational.

HT graphic
HT graphic

Once completed, the bridge will give motorists a direct link from Dindoshi to Sanjay Gandhi National Park, and eventually to the two underground tunnels that form the other major component of Phase 3.

Meanwhile, local MLA Mihir Kotecha has demanded termination of the contractor’s agreement, alleging repeated lapses in safety and housekeeping. He said the lack of barricades around deep excavation zones posed a threat to commuters, while dust, scrap and debris were left unattended. “ ₹14–15 crore is allocated for housekeeping alone. Work is behind schedule, conditions are unsafe, and BMC has issued 40 letters already. The penalties are paltry compared to the lapses,” Kotecha said.

The contractor could not be reached for comment.

  • Leena Raghunath Baliga
    ABOUT THE AUTHOR
    Leena Raghunath Baliga

    Leena Raghunath Baliga (byline: Linah Baliga) is Associate Editor with nearly two decades of experience in journalism,and has earlier worked with TOI, DNA and Mumbai Mirror specialising in civic affairs, urban governance and political reporting. Based in Mumbai, she has looked into the functioning of civic administration, public policy and governance, with a particular focus on the Brihanmumbai Municipal Corporation (BMC), urban infrastructure, housing, redevelopment and city planning. Over the years, she has consistently reported on issues that directly impact citizens, including municipal administration, public health, BEST, environmental concerns, major infrastructure projects and state government policies affecting urban development. Her reporting combines on-ground reporting, making complex civic and governance issues accessible to readers while ensuring accountability in civic administration. She has extensively covered political developments that shape urban policy. Her work has also focused on redevelopment policies, affordable housing and the implementation of major infrastructure projects across Mumbai.She continues to chronicle the evolving and changing landscape of Asia's richest municipal corporation. When she isn't chasing stories or poring over civic documents, she enjoys dabbling in art and unwinding with music. An avid rock 'n' roll enthusiast, she has an anachronistic taste in music, with a playlist that happily skips across decades, filled with timeless classics.Read More

Catch every big hit, every wicket with Crickit, a one stop destination for Live Scores, Match Stats, Infographics & much more. Explore now!

Stay updated with all the Breaking News and Latest News from Mumbai. Click here for comprehensive coverage of top Cities including Bengaluru, Delhi, Hyderabad, and more across India along with Stay informed on the latest happenings in World News.