MAHAKUMBH-2025 PREPARATION: Half-a-dozen ROBs more than 88% ready, relief for commuters soon

There are ROBs out of a total of 13 that are under construction in the district, whose works are now 88% or more complete

Published on: Nov 25, 2023, 20:17:01 IST
By , PRAYAGRAJ
Share
Share via
  • facebook
  • twitter
  • linkedin
  • whatsapp
Copy link
  • copy link

Various development works being undertaken in the run up to Mahakumbh-2025 in Prayagraj have now started gaining pace with their progress becoming visible on the ground.

For representation only (HT File Photo)
For representation only (HT File Photo)

According to the latest progress reports, there are six road over bridges (ROBs) out of a total of 13 that are under construction in the district, whose works are now 88% or more complete, even as the construction of another four ROBs has reached between 23% and 49%, district officials said.

It is believed that these ROBs will all be almost ready by March 2024. The confidence stems from the fact that 93% construction of the Mazar Trisection ROB and 94% construction of Bhirpur Meja Marg ROB are also complete while Bakshi Bandh ROB is 98% complete while Begam Bazar ROB is 91% finished while the Bampur Marg ROB is also 91% complete, the officials added.

Anirudh Kumar, project manager, UP Bridge Corporation, said that the construction of ROBs is being done at a fast pace. “Our target is to start traffic on some ROBs by March 2024 and the work on the remaining ROBs also gets 70 to 80 % completed by that time. The aim is to complete 98 to 99% of all construction work before the rains and make them operational immediately after the rains. We are confident of finishing the construction of all ROBs and make them operational well before the formal start of Mahakumbh-2025,” he added.

A report of this has also been sent to the state government by the UP Bridge Corporation, the officials said.

Officials concede that among the wide-ranging works being undertaken in the run up to Mahakumbh-2025, the most important at this time is the construction of the ROBs, roads and ghats.

  • K Sandeep Kumar
    ABOUT THE AUTHOR
    K Sandeep Kumar

    K. Sandeep Kumar is Senior Assistant Editor and Bureau Head of Hindustan Times in Prayagraj, where he leads the newspaper's editorial coverage across the region. With more than 25 years of experience in journalism, he has built a reputation for credible, in-depth and impact-driven reporting on Uttar Pradesh's governance, politics, education, agriculture, science and technology, defence, infrastructure and development. Over the course of his career, Sandeep has consistently broken and tracked stories that have shaped public discourse, with a particular focus on policy, public institutions and issues that directly affect people's lives. His reporting combines rigorous fieldwork with data-backed analysis, making complex subjects accessible to a wide readership. He has also written extensively on human-interest stories that spotlight resilience, innovation and social change across urban and rural Uttar Pradesh. As Prayagraj Bureau Head, he mentors reporters, drives editorial planning and ensures comprehensive coverage of one of India's most politically and culturally significant regions. His work is marked by accuracy, balance and context, reflecting a commitment to public-interest journalism and high editorial standards. Through his reporting, Sandeep continues to chronicle the evolving social, economic and political landscape of Uttar Pradesh while delivering insightful and reliable journalism for Hindustan Times readers.Read More