Ghaziabad’s summer power woes to go on
Residents of the city will face another grim summer due to non-completion of four 132KV power substations. Peeyush Khandelwal reports.
Residents of the city will face another grim summer due to non-completion of four 132KV power substations. The substations were expected to be completed by mid-2011. The irony is, the district contributes the highest power revenue among all the state’s districts.

Senior Uttar Pradesh Power Corporation Limited officials said the residents should expect 6-7 hours of scheduled power cuts this summer. “Due to delays and laxity, the work can only be completed by September or October 2011,” Chief Engineer (Transmission) AP Mishra said.
Last summer, Ghaziabad had seen 10-12-hour-long power outages a day due to severe load shedding. At present, the district is falling short by nearly 150MW. “What is painful is that residents pay taxes and yet have to pay more to make arrangements for power,” said Kuldeep Saxena from Indiapuram RWA.
ABOUT THE AUTHORPeeyush KhandelwalPeeyush Khandelwal writes on a range of issues in western Uttar Pradesh – from crime, to development authorities and from infrastructure to transport. Based in Ghaziabad, he has been a journalist for almost a decade.Read More
Stay updated with all top Cities including, Bengaluru, Delhi, Mumbai and more across India. Stay informed on the latest happenings in World News along with Delhi Election 2025 and Delhi Election Result 2025 Live, New Delhi Election Result Live, Kalkaji Election Result Live at Hindustan Times.

E-Paper