First three Metro lines to start operations by 2021, but car sheds not yet ready
Even as three Metro lines are scheduled for operations in 2020-21, they face a hurdle which may delay the plan – all of them don’t have car depots, an essential
Even as three Metro lines are scheduled for operations in 2020-21, they face a hurdle which may delay the plan – all of them don’t have car depots, an essential component to get the project off the ground. The three lines are part of the ambitious plan to get 13 Metro lines for the Mumbai Metropolitan Region (MMR) by 2026.

The Mumbai Metropolitan Region Development Authority (MMRDA) is looking at making line 2A (Dahisar-DN Nagar) and line 7 (Dahisar E-Andheri E) operational by the end of 2020, while the Mumbai Metro Rail Corporation (MMRC) is looking at making the first phase (Bandra-Kurla Complex-Aarey) of the underground Metro-3 (Colaba-Bandra-Seepz) corridor operational by December 2021.
The three lines together are expected to cater to more than 20 lakh commuters.
However, the Uddhav Thackeray-led Maha Vikas Aghadi has stayed construction of the controversial car depot for Metro-3 in Aarey Colony. While a committee appointed by the government stated that the depot should be in Aarey, the government is yet to decide. The MMRDA, on the other hand, recently terminated the contract of RCC-MBZ consortium that was building the car depot for 2A, 7 and line 2B (DN Nagar-Mandale) in Mandale.
As of today, 25% of the depot works have been completed in Aarey, while only 6.98% works have been completed in Mandale, where the MMRDA was expecting 50% work to be completed. The contract was awarded to RCC-MBZ in 2018 at a cost of ₹390 crore.
“We cannot start operations without a car depot,” said a senior official from MMRDA. An official from MMRC, who did not want to be named, said building a car depot would require 24 months.
The MMRC, on its website, defines the depot as a “mandatory and essential facility for smooth operations of any metro system where all metro trains rest during non-working hours. It is in the car depot that the trains can be washed, cleaned, repaired and maintained. It is the starting point for train operations every day”.
The first coaches for the lines will also arrive at the depot first, where it will be assembled. The MMRDA is expecting the first coach in July 2020, while the MMRC is expecting the first coach this December.
An official from MMRDA said while the authority will look for contractors to complete the depot works and take up portions of 2B, which were also awarded to the same contractor, the process will have a cascading effect on the work. “Delay is inevitable in such a situation. If we get contractors who are already working on other lines, too, the work will add to their burden. There can be procedural lapses also, for instance, if we get bids from only one contractor, then the whole process has to be repeated,” the official said.
The deadlines for the three lines have already been revised in the past. The earlier Devendra Fadnavis-led BJP government had set December 2019 as the deadline to initiate operations of line 2A and 7, while phase-1 of Metro-3 was earlier scheduled for June 2021.
ABOUT THE AUTHORTanushree VenkatramanTanushree Venkatraman is a Multimedia Correspondent covering civic issues and governance in Mumbai.
Stay updated with all the Breaking News and Latest News from Mumbai. Click here for comprehensive coverage of top Cities including Bengaluru, Delhi, Hyderabad, and more across India along with Stay informed on the latest happenings in World News.

E-Paper


