KRERA pulls up developer for failing to comply with its orders; slaps a penalty of up to 5% of the project cost

Bengaluru real estate: KRERA has held that a developer’s failure to comply with its directions attracts provisions under Section 63 of the RERA Act

Updated on: Apr 16, 2026 10:39 AM IST
Share
Share via
  • facebook
  • twitter
  • linkedin
  • whatsapp
Copy link
  • copy link

The Karnataka Real Estate Regulatory Authority (KRERA) has pulled up a developer for failing to comply with the authority's directions and orders and has imposed a penalty of up to 5% of the project cost.

Karnataka Real Estate Regulatory Authority has penalised a developer up to 5% of the project cost for non-compliance with its orders. (Picture for representational purposes only) (ChatGPT generated image )
Karnataka Real Estate Regulatory Authority has penalised a developer up to 5% of the project cost for non-compliance with its orders. (Picture for representational purposes only) (ChatGPT generated image )

“The Secretary, KRERA, to initiate penalty proceedings under Section 63 of the Act upon the Respondent Company for failure to comply with the earlier orders of this Authority. The penalty shall be cumulatively extended up to 5% of the estimated project cost payable within 60 days,” the order said.

The regulatory action comes after repeated non-compliance by Ozone Urbana Infra Developers Private Limited in refunding homebuyers, despite previous orders and subsequent enforcement proceedings initiated by the authority.

Also Read: KRERA pulls up developer for completion certificate delay, Mysuru buyers hit with 100% property tax penalty

The case

In this case, the homebuyers in the Ozone Urbana project had approached KRERA after facing significant delays and defaults by the developer in delivering the apartments. Citing failure to meet both contractual and statutory obligations, the complainants sought a refund of the amounts paid along with applicable interest.

“This authority, after affording sufficient opportunities to the developer and upon detailed consideration of the matter over a period of time, was pleased to pass orders in favour of the buyers directing the developer to refund 1.42 crore in one complaint and 1.13 crore in another vide order dated 05/08/2023 respectively along with specific directions issued to the developer for compliance within the stipulated period,” KRERA said.

However, despite the issuance of these orders, and even after execution proceedings were issued, initiated, and Recovery Certificates (RRCs) were issued, the developer failed to comply with the refund directions within the stipulated timelines, the order said.

“The buyers submit that such non-compliance constitutes a clear violation of the orders of this authority and attracts penal consequences under Section 63 of the Real Estate (Regulation and Development) Act, 2016, which provides for the imposition of a penalty for failure to comply with orders or directions of the Authority,” the authority said in the order.

The authority also said that, since the developer is a company, provisions under Section 69 would apply, making all individuals responsible for the conduct of its business, including directors, managers, and officers, liable under the Act.

“The earlier order was passed only against the company. The directors were not parties in the earlier proceedings. The corporate veil cannot be lifted routinely. The respondent further submits that RERA's jurisdiction extends only to promoters, allottees, and real estate agents. The directors cannot be fastened with liability absent specific allegations. The sale agreements were executed between the company and the complainants. The cirectors are not being signatories, cannot be made personally liable,” the order said.

A list of questions has been sent to the developer. The story will be updated once a response is received.

Also Read: KRERA pulls up Bengaluru developer for delay in issuing khata to a homebuyer

The order

KRERA held that the developer’s failure to comply with binding directions clearly falls within the provisions of Section 63 of the Real Estate (Regulation and Development) Act, 2016. The section provides for penalties for every day of default, cumulatively extendable up to 5% of the estimated project cost, it said.

“The order dated 05/08/2023 is undisputed. The burden to demonstrate compliance lies upon the developer once the existence of the order and lapse of the compliance period is established. The developer has not placed material demonstrating full compliance within the stipulated time,” it said.

Accordingly, KRERA has directed its secretary to initiate penalty proceedings against the company, with fines that could extend up to 5% of the project cost.

In addition, invoking Section 69 of the Act, the KRERA has issued a show-cause notice to the managing director and other directors responsible for the company’s operations during the relevant period. They have been asked to appear before the authority, either personally or through authorised representatives, within 30 days and explain why further penal action should not be initiated against them, the order said.

"The managing director and the directors who were responsible for the conduct of the business of the company during the relevant period shall appear either personally or through authorized representative before this Authority and show cause within 30 days as to why proceedings under Section 63 read with Section 69 of the Real Estate (Regulation and Development) Act, 2016 should not be initiated against theth for non-compliance of the orders of this Authority," the order said.

The impact

Calling it a landmark ruling, Advocate Akash Bantia, who also represented the homebuyers, said the order represents a significant shift in enforcement under the RERA Act, 2016. “This groundbreaking order by RERA marks the first-ever invocation of its penal provisions, imposing hefty penalties on the promoter for non-compliance with authority orders,” he said.

He further highlighted the wider implications of the ruling, pointing out that it “holds directors jointly and severally liable, unprecedented in RERA jurisprudence,” and sends a strong deterrent message to developers and their leadership teams.

  • Souptik Datta
    ABOUT THE AUTHOR
    Souptik Datta

    Souptik Datta is a deputy chief content producer at Hindustan Times Digital, where he reports on southern India with a focus on real estate, urban infrastructure and environmental urban issues. His coverage tracks the intersection of policy, capital flows, regulation and sustainability, examining how these forces shape housing markets, commercial real estate and large-scale infrastructure development across rapidly transforming cities. He also closely tracks civic issues affecting urban residents, including property taxation, planning approvals, public transport expansion, water stress, waste management and the governance challenges that influence everyday life in India’s metros. Souptik’s reporting is driven by a strong interest in accountability, consumer rights and the lived realities of homebuyers and investors navigating volatile pricing cycles, regulatory changes and project delivery risks. He frequently analyses project launches, land monetisation strategies, planning frameworks, RERA-related developments and the broader implications of infrastructure investments on emerging growth corridors. His work blends on-ground reporting with data-backed analysis and long-form explainers aimed at demystifying complex real estate and infrastructure developments for readers. He is an alumnus of the Indian Institute of Journalism and New Media. Before joining Hindustan Times Digital, Souptik was associated with Moneycontrol at Network 18, where he covered real estate, infrastructure and allied sectors, producing market insights, policy-led stories and in-depth features. Outside the newsroom, Souptik is an avid solo traveller and documentary enthusiast, exploring diverse regions and visually documenting unique narratives through film and photography. In his early career, Souptik also freelanced as a documentary photographer, independently working on visual storytelling projects that captured grassroots narratives, urban change and everyday life. He can be reached at souptik.datta@htdigital.in.Read More

Stay updated with latest Real Estate news and updates from India and around the World, explore the latest market moves and premium property listings updates now on Hindustan Times