Mahakumbh-2025: ₹54.32 crore released for two new ROBs in Prayagraj

The construction of two major rail overbridges (ROBs) in Tharwai and Soraon tehsils before Mahakumbh-2025 has gained momentum, with the government releasing the first instalment of 54.32 crore against the total budget of 217.88 crore. The tender will be issued in April, and after that, the construction work for projects sanctioned as part of preparations for Mahakumbh-2025 will start in the district.

Updated on: Mar 31, 2023, 18:14:34 IST
By , PRAYAGRAJ
Share
Share via
  • facebook
  • twitter
  • linkedin
  • whatsapp
Copy link
  • copy link

Contruction of two major rail overbridges (ROBs) before the start of Mahakumbh-2025 is now all set to gain momentum. The government has released the first instalment of 54.32 crore against the total budget of 217.88 crore for these two projects of UP State Bridge Corporation, say officials in the know of things. These two ROBs are to come up at Tharwai and Soraon tehsils. Now the tender will be issued in April, they add.

An under-construction ROB in Prayagraj. (HT file photo)
An under-construction ROB in Prayagraj. (HT file photo)

In view of Mahakumbh 2025, the apex committee had sent a proposal of 2500 crore for 86 projects to the government. Now, the government has started releasing funds for undertaking the proposed projects. A total budget of 71.19 crore was sought for ROB at Tharwai on Phaphamau-Padila road. The government has released an amount of 17.77 crore for it in first instalment.

At the same time, a total proposal of 146.69 crore was made for the ROB at Gohri in Shantipuram, against which an amount of 36.55 crore has been released.

The Uttar Pradesh State Bridge Corporation Ltd had sent a proposal for a total of five ROBs in Prayagraj. Officials say that the funds for the remaining three ROBs are also expected to be issued in the coming days.

It is expected that after April, the construction work for projects sanctioned as part of preparations for Mahakumbh-2025 will start in the district. The minister in-charge of the district Swatantra Dev Singh, who came to Prayagraj last week, had directed that the work on big projects should be expedited before the rain start in June-July.

Meanwhile, the obstacle of constructing the Salori ROB, being constructed near Teliarganj Mazar tri-section, has also been removed. For this, the government has released an additional budget of 9 crore. The government started the work for Salori ROB two years ago which is being built at a cost of about 46 crore.