MUMBAI: Construction of the proposed Gargai dam, a key water supply project aimed at augmenting Mumbai’s future water needs, is expected to begin in October 2026, with the reservoir likely to be filled by May 2029. The announcement was made by Abhijit Bangar, additional municipal commissioner (projects) at the standing committee on Wednesday.

Gargai dam work to begin in October 2026, completion targeted by 2029: BMC
Gargai dam work to begin in October 2026, completion targeted by 2029: BMC

The project includes a 69-metre-high dam near Ogada village and a 2.2-km tunnel that will channel water to the Modak Sagar reservoir. The Brihanmumbai Municipal Corporation (BMC) has targeted completion of the project by May 2029 and had proposed a budgetary provision of 437.51 crore for the Gargai project in its 2026–27 Budget Estimates.

Bangar said the dam will use roller compacted concrete (RCC) technology, a method that allows faster construction as the concrete does not require conventional curing. “The dam has RCC-type concrete and we need to place around 450mm concrete layers,” he said.

However, the project remains dependent on securing critical environmental clearances. “The most important approval is the forest diversion permission,” Bangar said, adding that two permissions from the Ministry of Environment, Forest and Climate Change (MoEFCC), along with approval from the National Board for Wildlife, are still pending.

According to officials, the delay in obtaining MoEFCC clearance stemmed from the lack of sufficient land for compensatory afforestation, a shortfall that has now been addressed.

The project has significant environmental and social implications, with two villages directly affected by submergence and four additional villages earmarked for relocation and rehabilitation.

An official said around 310,000 trees will be transplanted as part of the project mitigation measures. “Compensatory afforestation is planned across 658 hectares in Washim, Chandrapur and Hingoli, while all residents from affected villages will be shifted to Devali in Wada taluka with full infrastructure,” the official said.

The 658 hectares identified for compensatory afforestation will offset forest land diverted for the project. In addition, around 350 hectares of land spread across four of the six affected villages will be incorporated into forest land after transplantation measures are completed. Two villages are expected to be submerged due to the reservoir.

On rehabilitation, officials said nearly 400 hectares of land belonging to the Forest Development Corporation of Maharashtra in Devali, Wada taluka, has been identified for resettlement and rehabilitation of affected residents.

Meanwhile, preliminary technical work has already begun. Geotechnical soil investigations are underway at the site to assess ground conditions and finalise engineering specifications ahead of construction.

  • Leena Raghunath Baliga
    ABOUT THE AUTHOR
    Leena Raghunath Baliga

    Leena Raghunath Baliga (byline: Linah Baliga) is Associate Editor with nearly two decades of experience in journalism,and has earlier worked with TOI, DNA and Mumbai Mirror specialising in civic affairs, urban governance and political reporting. Based in Mumbai, she has looked into the functioning of civic administration, public policy and governance, with a particular focus on the Brihanmumbai Municipal Corporation (BMC), urban infrastructure, housing, redevelopment and city planning. Over the years, she has consistently reported on issues that directly impact citizens, including municipal administration, public health, BEST, environmental concerns, major infrastructure projects and state government policies affecting urban development. Her reporting combines on-ground reporting, making complex civic and governance issues accessible to readers while ensuring accountability in civic administration. She has extensively covered political developments that shape urban policy. Her work has also focused on redevelopment policies, affordable housing and the implementation of major infrastructure projects across Mumbai.She continues to chronicle the evolving and changing landscape of Asia's richest municipal corporation. When she isn't chasing stories or poring over civic documents, she enjoys dabbling in art and unwinding with music. An avid rock 'n' roll enthusiast, she has an anachronistic taste in music, with a playlist that happily skips across decades, filled with timeless classics.Read More

Catch every big hit, every wicket with Crickit, a one stop destination for Live Scores, Match Stats, Infographics & much more. Explore now!

Stay updated with all the Breaking News and Latest News from Mumbai. Click here for comprehensive coverage of top Cities including Bengaluru, Delhi, Hyderabad, and more across India along with Stay informed on the latest happenings in World News.