Jabalpur, Madhya Pradesh High Court Chief Justice RV Malimath has said lack of infrastructure comes in the way of increasing the number of judges in courts and without a long-term vision, pendency cannot be resolved and litigants will continue to suffer.

MP HC Chief Justice Malimath bats for long-term vision to resolve pendency and woes of litigants
MP HC Chief Justice Malimath bats for long-term vision to resolve pendency and woes of litigants

He was addressing a gathering here on Sunday after virtually laying the foundation stone of the MP High Court's infrastructure development in Jabalpur, Indore and Gwalior at a cost of 1,199.75 crore.

Get ready to catch the final stages of the World Cup only on Crickit. Anytime, Anywhere. Explore now!

"The lack of infrastructure is one of the primary reasons for not increasing the designated judges' strength. Without a long-term vision, pendency cannot be resolved, and litigants will continue to suffer," CJ Malimath said.

In future, the strength of judges in the MP High Court will go up to 121, including 60 at the principal seat in Jabalpur and 30 each at the Indore and Gwalior circuit benches, he said.

"We must put the needs of litigants before our own. I urge each one of you to put yourself in the shoes of a litigant, who has been waiting for decades to get justice. The plight of such litigants is unimaginable. It is only when we think from the litigant's perspective that we can rise above trivialities," he said.

"It is only when you rise above daily trifles that we can bring out the real change in the justice delivery system. A majority of us from the bar and the bench have been collectively doing it here in MP," CJ Malimath said.

He said the district court complex in Gwalior took 16 years for completion. The estimated time for the completion was 36 months and the project was sanctioned for 19.72 crore.

After much fast-tracking, the project was completed last month. The cost of the complex upon completion was a little more than 100 crore, he said.

"I hope these buildings do not take the same amount of time to be built. These new structures at Jabalpur, Indore and Gwalior are meant to aid dispensation of justice," he added.

CJ Malimath said the new complex of the MP State Judicial Academy here would be constructed at a cost of 485.84 crore and the new high court buildings in Indore and Gwalior at 307.68 core and 406.23 crore, respectively.

Justice S A Dharmadhikari, administrative judge of the Indore bench of HC, Justice Vivek Rusia, administrative judge of the HC's Gwalior bench, Justice Vivek Agarwal, in-charge chairman of the MP State Judicial Academy, Jabalpur and other judges of the MP high court were present at the function.

This article was generated from an automated news agency feed without modifications to text.

Get World Cup ready with Crickit! From live scores to match stats, catch all the action here. Explore now!

See more

Get Current Updates on India News, Budget 2024, Weather Today along with Latest News and Top Headlines from India and around the world.

SHARE THIS ARTICLE ON
SHARE
Story Saved
Live Score
OPEN APP
Saved Articles
Following
My Reads
Sign out
New Delhi 0C
Tuesday, June 25, 2024
Start 14 Days Free Trial Subscribe Now
Follow Us On