5th, 6th lines between Thane-Diva: MRVC seeks forest department nod to construct flyover

Hindustan Times | By, Mumbai
Published on: Jun 22, 2018 12:43 am IST

Building the flyover will involve cutting mangroves near Mumbra station

Under pressure to complete the laying of fifth and sixth rail lines between Thane and Diva by the March 2019 deadline, the Mumbai Railway Vikas Corporation (MRVC) has undertaken fresh efforts to speed up the process for getting permission from the forest department for constructing a flyover, by cutting mangroves near Mumbra station.

On a recent visit to Mumbai, Railway Board chairman Ashwani Lohani had instructed officials to complete laying fifth and sixth lines between Thane and Diva by the March 2019 deadline.(HT FILE)
On a recent visit to Mumbai, Railway Board chairman Ashwani Lohani had instructed officials to complete laying fifth and sixth lines between Thane and Diva by the March 2019 deadline.(HT FILE)

Acting on the railway board chairman Ashwani Lohani’s directive to complete the project by the set deadline during his Mumbai visit earlier this week, the MRVC has written to the forest department for permission to build a flyover in the area under mangrove cover. “We have started perusing the issue with the forest department freshly,” said a senior MRVC official.

MRVC officials said they have written to the Nagpur-based office of state forest department for permission. On the basis of their reply, the high court will grant permission for cutting mangroves to pave way for the 400 metre-long flyover.

Originally, the MRVC had planned to construct tunnels cutting Parsik hill adjacent to the existing tunnels on slow corridors, but due to some technical reasons, the authorities were forced to replace it with a flyover, for which cutting of mangroves is necessary.

According to MRVC officials, it will take at least six months to build the new flyover after getting the permission.

The project for laying fifth and sixth rail lines between Thane and Diva, which was sanctioned in 2008, is a part of Mumbai Urban Transport Project (MUTP 2B). The project will help the railways segregate outstation and suburban train operation between Kurla and Kalyan stations, by removing the bottleneck. Six lines already exist between Kurla-Thane and Diva-Kalyan.

The new lines will be parallel to the slow line between Thane and Diva. Once completed, these lines will be used for fast locals, whereas existing lines passing through Parsik tunnel will be used exclusively for outstation trains, the late arrival of which often affect the punctuality of locals.

The lines between Thane and Diva are being constructed by the MRVC and have a deadline of March 2019. The initial cost of the project was stated to be at 130 crore. However, the present cost is nearly 420 crore.

  • author-default-90x90
    ABOUT THE AUTHOR
    Kailash Korde

    Kailash works with the political team and has been covering transport beat for over a decade. He is interested in travel and music.

Catch every big hit, every wicket with Crickit, a one stop destination for Live Scores, Match Stats, Infographics & much more. Explore now!

Stay updated with all the Breaking News and Latest News from Mumbai. Click here for comprehensive coverage of top Cities including Bengaluru, Delhi, Hyderabad, and more across India along with Stay informed on the latest happenings in World News.
Catch every big hit, every wicket with Crickit, a one stop destination for Live Scores, Match Stats, Infographics & much more. Explore now!

Stay updated with all the Breaking News and Latest News from Mumbai. Click here for comprehensive coverage of top Cities including Bengaluru, Delhi, Hyderabad, and more across India along with Stay informed on the latest happenings in World News.
SHARE THIS ARTICLE ON
SHARE
Story Saved
Live Score
Saved Articles
Following
My Reads
Sign out
Get App
crown-icon
Subscribe Now!