Sign in

British Airways IT outage caused by contractor who switched off power: Report

BA had to cancel all flights from London’s Heathrow and Gatwick airports last Saturday. It blamed a power surge that knocked out its computer system.

Updated on: Jun 2, 2017, 21:59:31 IST
Reuters, London | By
Share
Share via
  • facebook
  • twitter
  • linkedin
  • whatsapp
Copy link
  • copy link

A contractor doing maintenance work at a British Airways data centre inadvertently switched off the power supply, knocking out the airline’s computer systems and leaving 75,000 people stranded last weekend, the Times newspaper reported on Friday.

People wait with their luggage at the British Airways check in desks at Heathrow Terminal 5 in London, Britain. (Reuters)
People wait with their luggage at the British Airways check in desks at Heathrow Terminal 5 in London, Britain. (Reuters)

Quoting a BA source, the newspaper said the power supply unit that sparked the IT failure was working perfectly but was accidentally shut down by a worker. An investigation into the power outage is likely to focus on human error rather than any equipment failure, it said.

BA had to cancel all flights from London’s Heathrow and Gatwick airports last Saturday. It blamed a power surge that knocked out its computer system, disrupting flight operations, call centres and its website.

Get the latest World News, breaking headlines and global updates from the US, UK, Pakistan, Bangladesh, Russia and other countries. Follow major international events on Hindustan Times.