Sign in

UAE licenses second unit of Barakah nuclear power plant

The plant in the Al Dhafrah Region of Abu Dhabi, capital of the UAE, is the first nuclear power plant in the Arab world and part of the Gulf oil producer's efforts to diversify its energy mix.

Published on: Mar 9, 2021, 16:06:57 IST
Reuters
Share
Share via
  • facebook
  • twitter
  • linkedin
  • whatsapp
Copy link
  • copy link

The United Arab Emirates Federal Authority for Nuclear Regulation has issued an operating licence for the second unit of the Barakah nuclear power plant, a UAE energy official said on Tuesday.

Barakah Nuclear Power Plant in the Gharbiya region of Abu Dhabi on the Gulf coastline about 50 kilometres west of Ruwais. (AFP)
Barakah Nuclear Power Plant in the Gharbiya region of Abu Dhabi on the Gulf coastline about 50 kilometres west of Ruwais. (AFP)

The plant in the Al Dhafrah Region of Abu Dhabi, capital of the UAE, is the first nuclear power plant in the Arab world and part of the Gulf oil producer's efforts to diversify its energy mix.

The licence was issued to the plant's operator Nawah Energy Company.

Barakah's Unit 1 was connected to the national power grid in August and in December reached 100% of reactor power capacity during testing.

Unit 1's test period is expected to end and commercial operations are expected to begin this year, Hamad Al Kaabi, the UAE Permanent Representative to the International Atomic Energy Agency (IAEA), told journalists.

When completed Barakah, which is being built by Korea Electric Power Corp (KEPCO), will have four reactors with 5,600 megawatts (MW) of total capacity.

Construction of Unit 3 is 94% complete and Unit 4 is 87% complete, Kaabi said.


Get the latest headlines from US news and global updates from Pakistan, Nepal, UK, Bangladesh, Russia and US Iran war Live, get all the latest headlines in one place on Hindustan Times.