SC extends demolition deadline of Noida's Supertech twin towers till August 28

According to the report, “Edifice Engineering now estimates an increase in blast floors, increase in holes per column, increase of wrapping of columns with wire mesh and geotextile cloth, increase in the quantity of explosives to be used, all of which is causing an additional delay of 9 to 10 weeks”
Following a site inspection about 10 days ago, CBRI submitted a report to Supreme Court regarding the preparation for the demolition and said it was in favour of an extension. (Sunil Ghosh/ HT Photo)
Following a site inspection about 10 days ago, CBRI submitted a report to Supreme Court regarding the preparation for the demolition and said it was in favour of an extension. (Sunil Ghosh/ HT Photo)
Updated on May 18, 2022 09:26 AM IST
Copy Link
ByAbraham Thomas

The Supreme Court on Tuesday extended the deadline for the demolition of the 32-storeyed twin towers—Apex and Ceyane—in Noida to August 28, three months beyond the earlier deadline set by the court for May 22.

The new date was requested by Edifice Engineering, the private firm contracted to demolish the towers.

A bench of justices Dhananjaya Y Chandrachud examined the application and found that it met the approval of an expert body – Central Building Research Institute (CBRI)--which, on May 11, communicated its approval for the time extension.

The bench said, “In view of expert opinion, time for completing the work of demolition is extended until August 28, 2022.”

The court also directed the Noida authority to convene a meeting of all stakeholders to discuss the steps to carry out the demolition safely and to file a status report before the next date of hearing on July 29.

Before passing the order, the court went through a status report prepared by the Noida authority, indicating that prior to seeking an extension, Edifice Engineering carried out a test blast on April 10 and found the structure sturdier than originally believed. Pursuant to this, Edifice Engineering wrote to Supertech, with a copy marked each to Noida authority and CBRI, with a request to reschedule the final blast date from May 22 to August 28 as it had to re-design the final building blast designs.

This report prepared by Edifice Engineering was presented to the top court by way of an application moved by Supertech’s interim resolution professional (IRP) Hitesh Goel.

Commenting on the application, advocate Gaurav Agrawal, assisting the court as amicus curiae, said, “If it is about safety, an extension may be granted and a report called in this regard by last week of July.”

Initially, even the court felt that it was a ploy by Supertech to delay the demolition that was ordered by the Supreme Court on August 31 last year.

But the court went by a report by CBRI, which is an expert body, that went into the four reasons cited by Edifice Engineering as grounds for seeking additional time.

According to the report, “Edifice Engineering now estimates an increase in blast floors, increase in holes per column, increase of wrapping of columns with wire mesh and geotextile cloth, increase in the quantity of explosives to be used, all of which is causing an additional delay of 9 to 10 weeks.”

Besides, Edifice Engineering attributed the delay to other factors such as interruptions caused by residents of Supertech’s Emerald Court society during the demolition of a nine-metre pathway between the two structures and adjacent towers, the damage to the IGL gas pipeline that required its re-routing, and delay by Supertech in making payments.

The order to demolish the twin towers was first issued by the Allahabad high court in April 2014 on a plea filed by the Emerald Court Apartment Owners’ Association. The residents complained that while purchasing the flats, the area occupied by the towers was shown as a green area and the towers that subsequently came up on this space amounted to a breach of trust by the builder. It also came to light that the structures were in violation of the National Building Code, 2005.

The Supreme Court, on an appeal filed by Supertech, upheld the high court verdict and ordered compensation to the homebuyers who bought flats in the twin towers. Of the 633 persons who booked flats in the twin towers, the court directed Supertech to refund the entire amount deposited by homebuyers with 12% interest. About 248 homebuyers took an early refund while 133 took flats in other Supertech projects, leaving only 252 homebuyers who were to receive a refund as per court’s order.

On February 7, 2022, a bench of justices Dhananjaya Y Chandrachud and Surya Kant directed that Supertech and Edifice Engineering implement the Supreme Court’s August 31, 2021 order to demolish the two buildings in Supertech Emerald Court society without further hold-up. Sources said that Edifice Engineering had earlier sought over four months for preparation. However, the Supreme Court gave them three months’ time, following which May 22 was fixed as the date for demolition.

SHARE THIS ARTICLE ON
Topics
Close Story
QUICKREADS

Less time to read?

Try Quickreads

  • One of the 14 Mughal-era gateways to punctuate the Walled City’s wall, the graceful Ajmeri Gate today is like a queen without her palace.

    Delhiwale: This way to Ajmeri Gate

    This venerable stone gateway originally signposted the way to the aforementioned pilgrim town. One of the 14 Mughal-era gateways to punctuate the Walled City’s wall, the graceful Ajmeri Gate today is like a queen without her palace.

  • Mahesh Choudhary, 45, went missing on April 4, 2007 and the case was registered five days later, after his son, Rakesh Choudhary, then 22, filed a missing complaint. (Representation purpose)

    Delhi: Cop’s hunt for kidnapper ends after a 15-year wait

    Assistant sub-inspector (ASI) Sanjeev Tomar’s quest ended on May 28, when he and members of his team arrested a man named Hari Om for abducting and killing Choudhary. Tomar, 47, now posted with the crime branch, was a constable at the Badarpur police station when the crime took place in 2007.

  • DFS chief Atul Garg said, “The addition of 89 new firefighting vehicles will help us improve our response time across Delhi”. (Photo by Amal KS /Hindustan Times)

    89 new trucks to help DFS speed up rescue operations

    The approval for purchasing 89 new fire trucks was sought against the condemnation of 60 fire trucks, which have diesel engines and have reached their expiry time of 10 years, and have to be taken off service.

  • Delhi minister Satyendar Jain. (ANI FILE)

    ED arrests 2 more in money laundering case against Delhi minister Satyendar Jain

    Vaibhav and Ankush were arrested under the provisions of Prevention of Money Laundering Act (PMLA). ED said both are directors of Ram Prakash Jewellers Pvt Ltd, which was raided on June 6. After the searches at premises linked to six people including the jewellery firm’s five directors, ED said it recovered 2.85 crore and 133 gold coins, alleging that the gold was from “unexplained sources” and was “secreted” in the properties.

  • A MCD official said enforcement teams seized 689.01 kg of plastic items and issued 368 challans on Friday.

    Problem of plenty: Ban no bar, Delhi markets struggle to get rid of plastics

    Following the latest notification of the Plastic Waste Management Rules, 2022 in February, the central government directed all states and union territories (UTs) to phase out SUPs in a planned manner by July 1, 2022.

SHARE
Story Saved
×
Saved Articles
Following
My Reads
Sign out
New Delhi 0C
Saturday, July 02, 2022