GMDA extends Dadi Sati flyover tender after no bids received
Officials and contractors cited rising construction costs and bitumen scarcity behind poor response to the ₹39.74 crore project.
The Gurugram Metropolitan Development Authority (GMDA) has extended the tender deadline for construction of a flyover at Dadi Sati Chowk after no company submitted bids for the ₹39.74 crore project, with officials and contractors citing rising construction costs and scarcity of bitumen as major reasons.

GMDA officials said the tender, floated on April 24, has now been extended till May 29 after no bids were received when it was opened on May 18.
The proposed 900-metre-long flyover is planned on the road connecting Elan Mall in Sector 84 with IMT Manesar. The six-lane structure, with three lanes on each side, is expected to ease congestion at Dadi Sati Chowk, which witnesses heavy traffic jams during morning and evening peak hours.
The development comes days after GMDA, on May 17, announced plans to construct underpasses at Dadi Sati Chowk and Shaheed Rao Ranjit Singh Chowk in addition to the flyovers proposed as part of traffic decongestion measures along the multi-utility corridor linking Dwarka Expressway and IMT Manesar.
A senior GMDA official admitted that no contractor had participated in the bidding process. “The tender has been extended till May 28 and contractors can submit their bids. High cost of inputs, scarcity of bitumen is a prime reason that there is reluctance among the contractors to take up civil and other works,” he said.
Contractors also alleged delays in release of payments by the authority. Responding to this, another GMDA official said payments are not delayed but the approval process is lengthy. “In comparison to GMDA, the payment system is easier in HSVP and PWD and thus the contractors prefer working for these agencies,” he said.
In another instance, GMDA had floated a ₹7.5 crore tender on April 17 for installation of emergency call boxes at major intersections. No bids were received when the tender opened on May 7, following which the deadline was extended twice. The tender is now scheduled to open on June 19.
ABOUT THE AUTHORAbhishek BehlAbhishek Behl is a Special Correspondent with Hindustan Times, Gurugram bureau. With over a decade of experience in journalism, he reports on Gurugram's rapid urban transformation, covering the city's changing infrastructure, governance, and planning landscape. His reporting spans major civic agencies, such as the Gurugram Metropolitan Development Authority (GMDA), Department of Town and Country Planning (DTCP), Haryana Shahari Vikas Pradhikaran (HSVP), and the National Highways Authority of India (NHAI). Behl has reported on key urban development issues such as RRTS projects, metro expansion, road and highway projects, water supply, drainage, mobility, environmental concerns, land use planning, affordable housing, and the city's real estate sector. He closely tracks policy decisions, infrastructure implementation, and their impact on the city and its residents. He also covers regulatory action against illegal constructions, urban flooding, traffic management, and initiatives aimed at improving civic services and sustainable development. Behl has also written on political developments in south Haryana, focusing on elections and governance. His journalism is driven by fact-based reporting, ground-level coverage, and an understanding of the social and economic dynamics of Gurugram. Apart from work he is a cyclist and a cricketer and a resident of Palam Vihar since 2010.Read More