Coastal road work remains on hold as HC refuses to lift stay

The judges, however, expressed willingness to allow the civic-appointed contractor to “strengthen” the work already done to protect it from damage during the monsoon.

Updated on: Apr 24, 2019, 06:54:04 IST
Hindustan Times, Mumbai | By
Share
Share via
  • facebook
  • twitter
  • linkedin
Copy link
  • copy link

The work on the ₹14,000-crore coastal road will remain stalled as the Bombay high court (HC) on Tuesday refused to vacate the stay on the ambitious civic project, which seeks to cut travel time between south Mumbai and the western suburbs by nearly 70%.

The HC has now posted the bunch of PILs for further hearing on June 2, after Aney and senior advocate Anil Sakhare, representing BMC, appeared hesitant to file the application on the work done on the project till now. (HT Photo)
The HC has now posted the bunch of PILs for further hearing on June 2, after Aney and senior advocate Anil Sakhare, representing BMC, appeared hesitant to file the application on the work done on the project till now. (HT Photo)

The division bench of Chief Justice Pradeep Nandrajog and Justice Nitin Jamdar, which was hearing a clutch of petitions challenging the project, also rejected a plea filed by the contractor, Larsen & Toubro (L&T) India Limited, wanting to be party to the public interest litigations (PILs).

The judges, however, expressed willingness to allow the civic-appointed contractor to “strengthen” the work already done to protect it from damage during the monsoon. “We understand that during the monsoon, the sea will be rough and the work done will get washed away, and requires protection,” the judges said, adding that the strengthening work will be permitted only under the supervision of a court commissioner, who will record it on video, and suggested the state and the civic body file an application, disclosing the work already done.

Earlier this month, while hearing petitions filed by a group of activists and a non-governmental organisation (NGO) — Society for Improvement of Greenery and Nature — raising environmental and ecological concerns about the coastal road, the HC had directed the Brihanmumbai Municipal Corporation (BMC), the nodal agency, to not carry out any new reclamation for the project until further orders. On April 16, the court had directed the BMC to maintain status quo by pausing all work on the project.

On Tuesday, senior advocate SU Kamdar, representing L&T, urged the court to allow the contractor to be a party to the proceedings as it will be directly affected by the orders. He submitted that L&T had already invested more than ₹300 crore in the project and the status quo order was hurting its pecuniary interests. He also said the work already completed will get washed away during the monsoon if the status quo order was not vacated. Senior advocate Shrihari Aney, representing the state, also tried to impress upon the HC that the interim order was required to be vacated in larger public interest.

The HC has now posted the bunch of PILs for further hearing on June 2, after Aney and senior advocate Anil Sakhare, representing BMC, appeared hesitant to file the application on the work done on the project till now.

While the group of activists, led by architect Shweta Wagh, have complained that the reclamation work flouts environmental laws and will irreversibly damage the coastal morphology of Mumbai, the NGO has expressed concerns about the loss of green cover which will occur if 200 trees in south Mumbai’s Tata Gardens are cut for the project.

  • HT News Desk
    ABOUT THE AUTHOR
    HT News Desk

    Follow the latest breaking news, major developments and agenda-setting stories from India and around the world with the newsdesk at Hindustan Times. Operating round the clock, the desk brings together experienced editors, reporters and correspondents to deliver fast, accurate and contextual reporting across subjects that influence public policy, governance, business, society and international affairs. The HT News Desk covers politics, elections, government policies, the economy, business and markets, science and technology, the environment, law and order, infrastructure, education, climate issues and geopolitics, while closely tracking developments across states, institutions and global capitals. The team also leads coverage of major breaking news events, policy announcements, court proceedings, natural disasters, public emergencies and significant international developments. Reports published by the newsdesk are based on information gathered from reporters on the ground, official statements, government agencies, court records, regulatory filings, recognised institutions and other authoritative sources. Stories undergo editorial scrutiny and verification processes to ensure accuracy, fairness and relevance, and are updated as events evolve and additional information becomes available. Whether covering a key political decision in New Delhi, an economic policy shift affecting millions, a landmark court ruling or a major global event, the HT News Desk aims to provide readers with reliable, fact-based journalism that delivers not only the latest developments but also the context and analysis needed to understand their wider implications.Read More