Consumer forum orders refund for delay in delivery of flats

The Imperia Esfera project was launched in 2012 in Sector 37-C and it comprised of around 580 flats in eight towers. The project was to be delivered in three years with a grace period of six months, said buyers.

Updated on: Sep 24, 2018, 15:34:24 IST
Hindustan Times, Gurugram | By , Gurugram
Share
Share via
  • facebook
  • twitter
  • linkedin
  • whatsapp
Copy link
  • copy link

The National Consumer Disputes Redressal Commission (NCDRC) has directed a builder to refund money paid by homebuyers, who had bought flats in its project in Sector 37 of Gurugram. Last week, the NCDRC, in two separate orders, directed Imperia Structures Ltd to refund 17 homebuyers, who had approached the commission for relief as their apartments had been delayed by more than three years.

The Imperia Esfera project was launched in 2012 in Sector 37-C and it comprised of around 580 flats in eight towers. The project was to be delivered in three years with a grace period of six months, said buyers. (HT FILE PHOTO)
The Imperia Esfera project was launched in 2012 in Sector 37-C and it comprised of around 580 flats in eight towers. The project was to be delivered in three years with a grace period of six months, said buyers. (HT FILE PHOTO)

The Imperia Esfera project was launched in 2012 in Sector 37-C and it comprised of around 580 flats in eight towers. The project was to be delivered in three years with a grace period of six months, said buyers, who approached the commission after they were told that possession could be given only by the end of 2020.

The bench of NCDRC president Justice RK Agarwal and member Justice M Shreesha held: “Keeping in view the admitted incomplete construction, the fact that some of the complainants have also taken bank loans and are paying EMIs and considering the stipulation provided in Clause11.4, this complaint is partly allowed directing the developer to refund the amounts deposited with simple interest at 9% pa from the respective dates of deposits till the date of realization, together with costs of 50,000/- to be paid to each of the complainants. The directions are to be complied within four weeks from the date of receipt of a copy of the order, failing which, the amount shall attract interest of 12%.”

The buyers said they wanted the order to be executed at the earliest. “We have been paying rent and EMI, both, in the hope that these homes would be handed over to us soon. It is very difficult to survive as majority buyers have paid an average of 60 to 70 lakh to the developer,” homebuyer and beneficiary of the directive, Rajat Verma, said.

The developer admitted that the project had been delayed because of reasons beyond its control.

“We have offered to these buyers alternative flats in the finished towers, where possession is being given. Also, penalty for delay in delivery is being paid to people as project timelines got delayed,” senior manager (customer relations management) of the Imperia Structures Ltd, Jasleen Khokhar, said.

  • Abhishek Behl
    ABOUT THE AUTHOR
    Abhishek Behl

    Abhishek Behl is principal correspondent, Hindustan Times in Gurgaon Bureau. He covers infrastructure, planning and civic agencies in the city. He has been covering Gurgaon as correspondent for the last 10 years, and has written extensively on the city.Read More

Catch every big hit, every wicket with Crickit, a one stop destination for Live Scores, Match Stats, Infographics & much more. Explore now!.

Stay updated with all the Breaking News and Latest News from Mumbai. Click here for comprehensive coverage of top Cities including Bengaluru, Delhi, Hyderabad, and more across India along with Stay informed on the latest happenings in World News.