With the 9.41km metro project in Ghaziabad nearing completion, the Delhi Metro Rail Corporation (DMRC) has submitted a ‘funding pattern’ as per the project’s updated completion cost. The eight-station elevated corridor project, connecting Dilshad Garden to New Bus Stand is now slated to be completed at a cost of ₹1,805 crore, down from the previous estimated of ₹2210 crore, said officials of the Ghaziabad Development Authority (GDA).
Authority officials Thursday said they had received written communication from the DMRC intimating them of the reduced completion cost (HT File Photo)
Authority officials Thursday said they had received written communication from the DMRC intimating them of the reduced completion cost. This includes the revised cost shares of the project to ₹272 crore for the DMRC, and ₹330 crore for the Centre. The cost share of state agencies has come down from ₹1,480 crore to ₹1,203 crore.