HC asks 2 society members to hand over flats, says redevelopment cannot be stalled indefinitely
MUMBAI: The Bombay High Court last week directed two members of a housing society who were holding up its redevelopment to hand over possession of their vacant flats to the developer within a week, observing that society members cannot indefinitely stall redevelopment by failing to come forward to execute individual permanent alternative accommodation agreements (PAAAs) with the developer
MUMBAI: The Bombay High Court last week directed two members of a housing society who were holding up its redevelopment to hand over possession of their vacant flats to the developer within a week, observing that society members cannot indefinitely stall redevelopment by failing to come forward to execute individual permanent alternative accommodation agreements (PAAAs) with the developer.

Their continued possession of their old flats, the court said, “has the effect of obstructing the redevelopment which the parties have agreed to undertake”.
A PAAA is a legal document in a redevelopment project that guarantees an existing property owner a replacement flat, shop or commercial premises and sets out arrangements such as temporary rent during construction.
The court’s ruling on September 17 came in the case of Charkop Dhanwantari Kabira Cooperative Housing Society (CDKCHS) in Kandivali, where two of the 36 members of the society had failed to execute their PAAAs with the developer. Dev Pooja Builders Private Limited (DPBPL) had moved the court against the two members and the housing society, contending that the alleged breach of the development agreement (DA) had delayed the redevelopment process as the old building could not be demolished unless all its members handed over vacant possession of their flats.
The CDKCHS, comprising two 35-year-old buildings with 36 occupants, entered into a development agreement with DPBPL on August 26, 2025. On July 10, the developer issued a notice informing the society that he had obtained all the necessary permissions and asked its members to sign their individual consent letters. Members who signed the letters were required to vacate their premises within 30 days.
Under the DA, each member of the society was to receive a new flat or shop, based on their existing premises, with an additional area equivalent to 41% of their existing premises, along with one car parking space for each member, a corpus for maintenance in the new building, transit fund, rent, brokerage and shifting charges.
However, the 30-day period to vacate the premises lapsed on August 10. The developer informed the court that, except for two members — Vilas Gaikwad and Suhas Bhalerao — all other members had vacated their flats. He stated that the building could not be demolished unless all members vacated their premises.
Bhalerao’s lawyer, however, told the court that the developer’s plea was premature. He stated that registration of the individual PAAA was a condition that had to be met before compulsory vacation of the premises. He said that there could not be a breach of the DA when the developer had not registered the PAAA.
A single-judge bench of Justice Amit Borkar said, “The immediate question is whether interim protection is required so that the redevelopment agreed between the parties is not stopped because of the non-cooperation of two members. The developer’s case was not that the two members had refused to accept the PAAA but that they were not coming forward to execute it.
The court took note of a clause in the DA that stated that the developer “shall be fully entitled to seek vacation of the premises held by the members” for redevelopment of the property.
The clause, the court said, “Cannot be understood to mean that a member can keep the redevelopment stopped for an unlimited period by refusing to come forward for execution of the individual agreement and taking the position that the agreement has not been registered”.
The court said the developer had already executed the PAAA with 34 other members and was ready to do the same with the two members before the court. They, the court said, “cannot keep the redevelopment stopped for an indefinite period by not completing the step which they are required to complete”.
The two members, who may have some disagreements over the area of their alternative accommodation, the court said, “cannot be permitted to stop the redevelopment contrary to the arrangement entered into under the Development Agreement.”
Stay updated with all the Breaking News and Latest News from Mumbai. Click here for comprehensive coverage of top Cities including Bengaluru, Delhi, Hyderabad, and more across India along with Stay informed on the latest happenings in World News.

E-Paper

