UP plans ₹ 5,525-crore battery storage projects at six locations
IIT-BHU study identifies 4,250 MW storage potential at thermal power stations, systems to help meet peak demand
Uttar Pradesh Rajya Vidyut Utpadan Nigam Ltd (UPRVUNL), a state-owned power generation utility, plans to develop battery energy storage systems (BESS) at six locations linked to its thermal power stations with a combined storage potential of 4,250 MW and an estimated investment of ₹5,525 crore, officials said.

“Commissioned by us, a feasibility study by the Indian Institute of Technology (BHU), Varanasi, has identified the storage potential which could help the state manage peak electricity demand, improve power availability during evening and night, and reduce dependence on costly power purchases from the market,” UPRVUNL managing director Mayur Maheshwari said.
BESS works like a giant rechargeable battery, storing surplus electricity when available and releasing it when needed if demand rises and available power falls short of the requirement. An inverter converts the stored energy into grid-compatible electricity for supply to the grid.
Prior to the advent of BESS technology, there was no way to store electricity which had to be consumed as and when it was generated.
The proposed projects seek to address the mismatch between power availability and demand in the state. During the day, when solar power is also available, electricity availability usually exceeds demand. The situation changes in the evening and at night when demand peaks, solar generation is unavailable and available power falls short of the requirement, especially in summers.
“The battery systems will help bridge this gap by storing electricity generated by the thermal stations and, when available, solar power, for use during peak-demand hours,” Maheshwari explained, adding “This will help make better use of electricity available during the day and provide an additional source of supply when demand rises.”
The proposed storage capacity includes 500 MW at Anpara, 100 MW at Obra, 150 MW each at Harduaganj, Panki and Parichha. Jawaharpur in Etah has the largest identified potential at 3,200 MW. Together, the six locations account for 4,250 MW of storage capacity.
The estimated total investment is ₹5,525 crore, including ₹4,160 crore for the Jawaharpur installation.
Maheshwari said that the existing and identified thermal power station sites had land, switchyard and power evacuation infrastructure that could facilitate the development of battery storage facilities.
The systems are proposed to use Lithium iron Phosphate (LFP) battery technology with liquid cooling. The specified storage duration is four hours with a single cycle. The estimated cost is ₹1.25 crore to ₹1.3 crore per MW, while the space requirement is 1.5 to two acres for every 100 MW of storage capacity. The cost model is to follow Central Electricity Regulatory Commission (CERC) guidelines.
The proposal comes as the state plans for its future electricity requirements. The Central Electricity Authority’s Resource Adequacy Report for the state for 2006-27 to 2035-36 has projected an additional energy storage requirement of 52,977 MW.
“The 4,250 MW potential identified at our six locations would be equivalent to around 8% of that storage requirement projected by the CEA,” a technical expert and UPRVUNL official Sanjay Gupta said.
The proposed projects, according to him, could support grid stability, improve energy security and help the state make better use of available electricity. “They could also generate investment and employment opportunities while contributing to the state’s clean energy transition,” he pointed out.
ABOUT THE AUTHORBrajendra K ParasharBrajendra K Parashar is a Senior Journalist with the Hindustan Times, based in Lucknow, with nearly three decades of experience covering governance, public policy, politics and development in Uttar Pradesh. Over the years, he has reported extensively on key sectors, including energy and renewable power, mobility and transport, road safety, agriculture and allied sectors and issues related to farmers, rural development, taxation under the Goods and Services Tax (GST) and public administration. A seasoned political correspondent, Parashar closely tracks the Bharatiya Janata Party (BJP) and has covered every major election in Uttar Pradesh right from three-tier panchayat elections and urban local body polls to Assembly and Lok Sabha elections. He also reports regularly on the proceedings of the Uttar Pradesh Legislature, bureaucracy, governance, policy decisions and administrative developments with focus on their impact on public life. His reporting is known for its strong analytical approach, extensive use of official data. His areas of interests include investigative journalism, long-form political and policy analysis, data-driven reporting, elections and institutional reforms. Parashar holds a postgraduate degree in Political Science with First Division from Aligarh Muslim University (AMU), followed by a Diploma in Journalism and Mass Communication from the same university. His inclination towards journalism began during his student days, when he regularly contributed letters to editors and articles to newspapers and magazines. In the mid-1990S, his essay, “Should India Switch Over to the Presidential Form Of Government?”, published in Politics India magazine edited by noted constitutional expert Subhash C Kashyap, was adjudged the best entry in a national competition. His work has received professional recognition, including the Hindustan Times Journalist of the Month Award for an impactful series on drinking water issues during the 2010 Lok Sabha election campaign. Originally from Kasganj in western Uttar Pradesh, Parashar is currently based in Lucknow where continues to report on politics, governance and public policy.Read More